Development of a Decision Support System for Production Scheduling of Precast Concrete Members

프리캐스트 콘크리트 부재의 생산일정 계획을 위한 의사결정 지원시스템 개발

  • Received : 2015.08.05
  • Accepted : 2016.02.15
  • Published : 2016.02.29

Abstract

Precast concrete technology is being actively investigated once again by domestic construction conglomerates and precast concrete production companies as a solution to labor supply problem due to labor cost increase and shortening of high-rise building construction time. Especially, the production scheduling of precast concrete members is an important management step directly affecting the economics of the technology and the construction schedule at the construction site. Nonetheless, there is no manual or a program of standardized process, to which a production manager can conveniently refer up until now, in the establishment of a production scheduling of precast concrete members. This causes inefficiency of its production schedule. Thus, this study aimed at developing the process and system, which can conveniently establish the production schedule for precast concrete members for the production companies, after the determination of the assembly schedule of the member at the construction site. The result of this study will contribute to satisfy the deadline for the production of the member for its production companies. And it is believed to be used as an efficient decision making system in the establishment of a production schedule of precast concrete members to promote the efficiency of the mold usage plan. Further, it is expected to be used as a guideline for the production manager to establish the production schedule of precast concrete members.

Keywords

References

  1. An, S., Lee, U., Kang, K. (2004). A Study on the Proposal about the Improvement of PC in Construction Industry, Journal of the Architectural Institute of Korea, Construction Section, 20(7), 135-152.
  2. Chan, W., Hu, H. (2002). Production Scheduling for Precast Plants using a Flow Shop Sequencing Model, Journal of Computing in Civil Engineering, 16(3), 165-174. https://doi.org/10.1061/(ASCE)0887-3801(2002)16:3(165)
  3. Hu, H. (2007). A Study of Resource Planning for Precast Production, Architectural Science Review Volume 50.2, 106-114. https://doi.org/10.3763/asre.2007.5016
  4. Hwang, J. (2014). Development of Integrated Management Process for Precast Concrete Construction Method based on BIM, Thesis, The University of Seoul..
  5. Jo, K. (2006). A Study on the Integrated and Revitalization of Prefabricated with Precast Concrete, Thesis, Inha University.
  6. Kim, D. (2008). Efficient Production Process for Precast Concrete Members, Thesis, Soongsil University.
  7. Korea National Housing Corporation, (1997). Development of Production-Translation-Installation Integrated System for the Large Panel P.C Constructiona.
  8. Kwahk, G., Sohn, J., Kim, K., Sohn, C., Kim, J. (1998). A Logistics Information Management System for the Prefabricated Precast Concrete Panels, Journal of the Architectural Institute of Korea, Construction Section, 14(10), 87-94.
  9. Park, Y. (2013). A Schedule and Cost Optimization System for PC Product Operation, Thesis, Kyungpook University.
  10. Song, K. (2005). PC Production Schedule Optimization Model Using a Genetic Algorithms and Random Keys, Proceedings of annual conference of the Architectural Institute of Korea, Construction Section, 25(1). (Received Aug. 5 2015 Revised Sep. 17 2015 Accepted Feb. 15 2016)