A Study on the Quantitative Risk Level Calculation Model in Cooperation with the Reserve Fund

예비비와 연계한 정량적 리스크 수준 산정 모델에 관한 연구

  • Kwoak, Song-Hae (Dept. of Computer Engineering, Kongju National University) ;
  • Park, Koo-Rack (Dept. of Computer Science & Engineering, Kongju National University) ;
  • Kim, Dong-Hyun (Dept. of IT Convergence, Woosong University)
  • 곽송해 (공주대학교 컴퓨터공학과) ;
  • 박구락 (공주대학교 컴퓨터공학부) ;
  • 김동현 (우송대학교 IT융합학부)
  • Received : 2016.08.16
  • Accepted : 2016.10.20
  • Published : 2016.10.28

Abstract

Recent public information project, which has been organized mainly to large companies is a situation that is being reorganized to small and medium-sized systems integration company. However, many of the small and medium-sized companies lack knowledge of the systematic risk management. Thus, in connection with the revenue, it involves a number of problems. Therefore, in this paper, we present a risk element that occurs mainly in the field of the project, providing a model for measuring the risk element by risk level costs associated with this. Through the convergence, we aim at providing a management system that is able to make the project successfully accomplished, predicting the risk that occurs in advance to pursue the project; Based on the proposed model, it is possible to secure a proper size of reserve fund so it is expected to enable companies to ensure the cost of risk analysis.

최근에 대기업 위주로 편성되어 있던 공공정보화 프로젝트가 중소규모의 시스템 통합 기업으로 재편성되고 있는 상황이다. 그러나 대다수의 중소규모 기업들은 체계적인 리스크 관리에 대한 지식을 확보하지 못하고 있기에, 수익과 관련하여 많은 문제를 내포하고 있다. 이에 본 논문에서는 프로젝트 현장에서 주요하게 발생하는 리스크 요소를 제시하고, 리스크 요소별 리스크 수준과 이에 따른 비용을 측정하기 위한 모델을 제안한다. 이러한 융복합을 통하여 프로젝트 수행 중 이슈화 되는 리스크를 사전에 예측하여 프로젝트를 성공적으로 수행하기 위한 관리 체계를 제공하는 데 목적을 두고 있으며, 제안 모델을 기준으로 적정한 규모의 예비비 확보가 가능하기에 리스크 분석에 비용을 투자하지 못하는 기업들이 활용할 수 있을 것으로 기대된다.

Keywords

References

  1. H. H. Park, H. O. Nho, Y. H. Kim, "The Impact of Perceived IT Threat on Convergence Information System Performance", Journal of the Korea Convergence Society, Vol. 6, No. 3, pp. 65-71, 2015. https://doi.org/10.15207/JKCS.2015.6.3.065
  2. Y. J. Kim, "Convergence of Business Information System Process using Knowledge-based Method", Journal of the Korea Convergence Society, Vol. 6, No. 4, pp. 65-71, 2015. https://doi.org/10.15207/JKCS.2015.6.4.065
  3. Duncan, W. R., "A Guide to the Project Management Body of Knowledge 2000 Edition", Project Management Institute, 2000.
  4. K. R. Park, "A Study of the Functional Requirements to Management Tool for Software Development Projects", Journal of Korea Society of Computer Information, Vol. 16, No. 12, pp. 113-120, 2011. https://doi.org/10.9708/jksci.2011.16.12.113
  5. J. B. Lee, Y. H. Jang, S. Y. Kim, "A Research on the PMO Functions and PMO Management Level to Increase the IS Project Performance", Journal of Digital Convergence, Vol. 9, No. 2, pp. 111-129, 2011.
  6. C. Y. Jung, D. K. Son, "An Exploratory Study for the Evaluation of Risk Factors in Information System Development using AHP", Journal of Korea Association of Information Systems, Vol. 15, No. 2, pp. 77-93, 2006.
  7. Boehm, B., Turner, R., "Management Challenges to Implementing Agile Process in Traditional Development Organizations", IEEE Software, Vol. 22, No. 5, pp. 30-39, 2005.
  8. Barki, H., Rivard, S., Talbot. J., "Toward an assessment of software development risk", Journal of Management Information Systems, Vol. 10, No. 2, pp.203-225, 1993. https://doi.org/10.1080/07421222.1993.11518006
  9. T. D. Kim, H. W. Lee, "The Research Regarding an Information System Risk Management Process Characteristics", Journal of Korea Information Processing Society, Part D, pp. 303-310, 2007.
  10. H. K. Park, "The Role of Project Management Office(PMO) for Implementing Successful Information Technology Project in Financial Industry", Master's Thesis, Yonsei University, 2011.
  11. S. N. Hong, "A Case Study on Risk Factors and Risk Management in a Large-scale Project", Journal of Korea Association of Information Systems, Vol. 19, No. 1, pp. 97-116, 2010.
  12. S. J. Lee, H. J. Kim, H. S. Suh, "Exploratory Study on Risk Factors by Project Performance Areas in Software Project Management", Journal of Information Technology Applications and Management, Vol. 11, No, 4, pp. 103-120, 2004.
  13. K. R. Park, "A Study on Project Management System", Journal of Digital Convergence, Vol. 13, No. 1, pp. 305-311, 2015.
  14. H. K. Jeon, K. R. Park, J. Y. Jung, "A Study on Software Dev. Project Management System Acquisition and Implementing on Project Site", Journal of Korea Society of Computer Information, Vol. 20, No. 5, pp. 91-98, 2015. https://doi.org/10.9708/JKSCI.2015.20.5.091
  15. D. K. Son, C. Y. Jung, "Risk Factors in the Information System Development Project", Proceeding of Korea Society of IT Services, pp. 355-362, 2003.
  16. Bell, T. E., "Management Murphy's Law: engineering a minimum risk system", IEEE Spectrum, Vol. 26, No. 6, pp. 24-27, 1989. https://doi.org/10.1109/6.29335
  17. Boehm, B. W., "Software Risk Management", Los Alamitos, CA: IEEE Computer Society Press, 1989.
  18. Y. H. Lee, "A Study on Estimating the Optimal Management Reserve of System Integration Project", Master's Thesis, Soongsil University, 2006.