Developing IoT-based Construction Progress Measurement Prototype

사물인터넷 기반 건설 프로젝트 성과측정원형 개발

  • 이형국 (경북대학교 건설환경에너지공학부 대학원) ;
  • 이홍철 (경북대학교 건설환경에너지공학부 대학원) ;
  • 이동은 (경북대학교 건축토목공학부)
  • Received : 2015.09.01
  • Accepted : 2015.11.10
  • Published : 2015.11.30

Abstract

Conventional progress control technique which collects and manages construction progress data manually is involved in inaccurate and omitted information in construction phase. It is time consuming and labor intensive to acquire the construction operation data in detail. It is important to develop the system that analyzes the project performance accurately and control the progress efficiently by keeping track of the progress data at a lower level than the operation. This paper proposes a system prototype which measures project progress at the construction operation level by hybridizing remote-controlled robots (i.e., air-drone and wheel mounted vehicle), smart sensors, and project scheduling and controlling tool. The system is developed into an Internet of Thing(IoT)-based progress measurement system. using robot and information technology. Earned value method-based physical progress measurement method is utilized to compute the quantity of work completed. A test case was performed to confirm that the new system complements the limitation of existing progress control method.

Keywords

Acknowledgement

Supported by : 한국연구재단

References

  1. Abdelsayed, M., & Navon, R. (1999). An information sharing, Internet-based, system for project control. CIVIL ENGINEERING SYSTEMS, 16(3), 211-233. https://doi.org/10.1080/02630259908970263
  2. Abdel Aziz, A. M. (2008). Minimum performance bounds for evaluating contractors performance during construction of highway pavement projects. Construction Management and Economics, 26(5), 507-529. https://doi.org/10.1080/01446190801918748
  3. Ashton, K. (2009). That 'internet of things' thing. RFiD Journal, 22, 97-114.
  4. Bernold, L. E. (1990). Bar code-driven equipment and materials tracking for construction. Journal of Computing in Civil Engineering, 4(4), 381-395. https://doi.org/10.1061/(ASCE)0887-3801(1990)4:4(381)
  5. Bosche, F., & Haas, C. T. (2008). Automated retrieval of 3D CAD model objects in construction range images. Automation in Construction, 17(4), 499-512. https://doi.org/10.1016/j.autcon.2007.09.001
  6. Briones, L., Bustamante, P., & Serna, M. A. (1994). Wall-climbing robot for inspection in nuclear power plants. In Robotics and Automation, 1994. Proceedings., 1994 IEEE International Conference on (1409-1414). IEEE.
  7. Bjork, B. C. (1999). Information Technology in Construction-domain definition and research issues. International Journal, 1(1), 3-16.
  8. Caldas, C. H., Torrent, D. G., & Haas, C. T. (2006). Using global positioning system to improve materials-locating processes on industrial projects. Journal of Construction Engineering and Management, 132(7), 741-749. https://doi.org/10.1061/(ASCE)0733-9364(2006)132:7(741)
  9. Cheung, S. O., Suen, H. C., & Cheung, K. K. (2004). PPMS: a web-based construction project performance monitoring system. Automation in construction, 13(3), 361-376. https://doi.org/10.1016/j.autcon.2003.12.001
  10. Clark, F., & Lorenzoni, A. B. (1996). Applied cost engineering. CRC Press.
  11. Davidson, I. N., & Skibniewski, M. J. (1995). Simulation of automated data collection in buildings. Journal of computing in civil engineering, 9(1), 9-20. https://doi.org/10.1061/(ASCE)0887-3801(1995)9:1(9)
  12. DeVault, J. E. (2000). Robotic system for underwater inspection of bridge piers. Instrumentation & Measurement Magazine, IEEE, 3(3), 32-37.
  13. Eldin, N. N. (1989). Measurement of work progress: Quantitative technique. Journal of construction engineering and management, 115(3), 462-474. https://doi.org/10.1061/(ASCE)0733-9364(1989)115:3(462)
  14. El-Omari, S., & Moselhi, O. (2011). Integrating automated data acquisition technologies for progress reporting of construction projects. Automation in Construction, 20(6), 699-705. https://doi.org/10.1016/j.autcon.2010.12.001
  15. Finch, E. F., Flanagan, R., & Marsh, L. E. (1996). Electronic document management in construction using auto-ID. Automation in construction, 5(4), 313-321. https://doi.org/10.1016/S0926-5805(96)00156-2
  16. Fleming, Q. W., & Koppelman, J. M. (1996). Earned value project management. Project Mangement Institute.
  17. Ghanem, A. G., & AbdelRazig, Y. A. (2006). A framework for real-time construction project progress tracking. Earth and space, 188(112).
  18. Halpin, D. W., and Riggs, L. S. (1992). Planning and Analysis of Construction Operation. John Wiley and Sons Inc., USA.
  19. Howes, N. R. (1984). Managing software development projects for maximum productivity. Software Engineering, IEEE Transactions on, (1), 27-35.
  20. Huston, D., Esser, B., Miller, J., & Wang, X. (2003). Robotic and mobile sensor systems for structural health monitoring. In Proceedings of the 4th International Workshop on Structural Health Monitoring, Stanford, CA, September (Vol. 1517).
  21. Hwang, B. G., Zhao, X., & Ng, S. Y. (2013). Identifying the critical factors affecting schedule performance of public housing projects. Habitat International, 38, 214-221. https://doi.org/10.1016/j.habitatint.2012.06.008
  22. Jung, Y., & Kang, S. (2007). Knowledge-based standard progress measurement for integrated cost and schedule performance control. Journal of Construction Engineering and Management, 133(1), 10-21. https://doi.org/10.1061/(ASCE)0733-9364(2007)133:1(10)
  23. Kim, C., Son, H., & Kim, C. (2013). Automated construction progress measurement using a 4D building information model and 3D data. Automation in Construction, 31, 75-82. https://doi.org/10.1016/j.autcon.2012.11.041
  24. Ko, C. H. (2009). RFID-based building maintenance system. Automation in Construction, 18(3), 275-284. https://doi.org/10.1016/j.autcon.2008.09.001
  25. La Rosa, G., Messina, M., Muscato, G., & Sinatra, R. (2002). A low-cost lightweight climbing robot for the inspection of vertical surfaces. Mechatronics, 12(1), 71-96. https://doi.org/10.1016/S0957-4158(00)00046-5
  26. Latham, M. (1994). Constructing the team: joint review of procurement and contractual arrangements in the United Kingdom construction industry. Final Rep.
  27. Lee, D., & Lee, S. (2014), Research of IoT in industrial site, Journal of Advanced Information Technology and Convergence, 12(1), 29-34
  28. Lee, B. (1996), Improvement of calculating method of Construction progress and completed amount measurement, Construction Economy Research Institute of Korea, 1-59
  29. Lin, Y. C., Cheung, W. F., & Siao, F. C. (2014). Developing mobile 2D barcode/RFID-based maintenance management system. Automation in Construction, 37, 110-121. https://doi.org/10.1016/j.autcon.2013.10.004
  30. Love, P. E., Irani, Z., & Edwards, D. J. (2004). Industry-centric benchmarking of information technology benefits, costs and risks for small-to-medium sized enterprises in construction. Automation in construction, 13(4), 507-524. https://doi.org/10.1016/j.autcon.2004.02.002
  31. Love, P. E., & Irani, Z. (2004). An exploratory study of information technology evaluation and benefits management practices of SMEs in the construction industry. Information & Management, 42(1), 227-242. https://doi.org/10.1016/j.im.2003.12.011
  32. Lopez, J., Perez, D., Paz, E., & Santana, A. (2013). WatchBot: A building maintenance and surveillance system based on autonomous robots. Robotics and Autonomous Systems, 61(12), 1559-1571. https://doi.org/10.1016/j.robot.2013.06.012
  33. Navon, R., Goldschmidt, E., & Shpatnisky, Y. (2004). A concept proving prototype of automated earthmoving control. Automation in Construction, 13(2), 225-239. https://doi.org/10.1016/j.autcon.2003.08.002
  34. Navon, R. (2005). Automated project performance control of construction projects. Automation in Construction, 14(4), 467-476. https://doi.org/10.1016/j.autcon.2004.09.006
  35. Navon, R. (2007). Research in automated measurement of project performance indicators. Automation in Construction, 16(2), 176-188. https://doi.org/10.1016/j.autcon.2006.03.003
  36. Metni, N., & Hamel, T. (2007). A UAV for bridge inspection: Visual servoing control law with orientation limits. Automation in construction, 17(1), 3-10. https://doi.org/10.1016/j.autcon.2006.12.010
  37. Oh, J. K., Jang, G., Oh, S., Lee, J. H., Yi, B. J., Moon, Y. S., & Choi, Y. (2009). Bridge inspection robot system with machine vision. Automation in Construction, 18(7), 929-941. https://doi.org/10.1016/j.autcon.2009.04.003
  38. Peyret, F., Betaille, D., & Hintzy, G. (2000). High-precision application of GPS in the field of real-time equipment positioning. Automation in Construction, 9(3), 299-314. https://doi.org/10.1016/S0926-5805(99)00058-8
  39. Poirier, C. C., & McCollum, D. (2006). RFID strategic implementation and ROI: a practical roadmap to success. J. Ross Publishing.
  40. Sacks, R., Navon, R., & Goldschmidt, E. (2003). Building project model support for automated labor monitoring. Journal of computing in civil engineering, 17(1), 19-27. https://doi.org/10.1061/(ASCE)0887-3801(2003)17:1(19)
  41. Sacks, R., Navon, R., & Brodetskaia, I. (2006). Interpretation of automatically monitored lifting equipment data for project control. Journal of computing in civil engineering, 20(2), 111-120. https://doi.org/10.1061/(ASCE)0887-3801(2006)20:2(111)
  42. Saidi, K. S., Lytle, A. M., & Stone, W. C. (2003). Report of the NIST workshop on data exchange standards at the construction job site. In Proc., ISARC-20th Int. Symp. on Automation and Robotics in Construction (617-622). Eindhoven, The Netherlands.
  43. Schempf, H., Mutschler, E., Goltsbergm, V., & Crowley, W. (2003). Grislee: Gasmain repair and inspection system for live entry environments. The International Journal of Robotics Research, 22(7-8), 603-616. https://doi.org/10.1177/02783649030227009
  44. Turkan, Y., Bosche, F., Haas, C. T., & Haas, R. (2012). Automated progress tracking using 4D schedule and 3D sensing technologies. Automation in Construction, 22, 414-421. https://doi.org/10.1016/j.autcon.2011.10.003
  45. Thomas, H. R., & Mathews, C. T. (1986). An analysis of the methods for measuring construction productivity. Construction Industry Institute, University of Texas at Austin [distributor].
  46. Wakisaka, T., Furuya, N., Inoue, Y., & Shiokawa, T.(2000). Automated construction system for high-rise reinforced concrete buildings. Automation in Construction, 9(3), 229-250. https://doi.org/10.1016/S0926-5805(99)00039-4
  47. Xu, F., & Wang, X. (2008, July). Design and experiments on a new wheel-based cable climbing robot. In Advanced Intelligent Mechatronics, 2008. AIM 2008. IEEE/ASME International Conference on (418-423). IEEE.
  48. Yoon, S. (2003), A progress measurement method based on characteristics of work types, Masteral dissertation, Graduate school of Sungkyunkwan University, Seoul.