Abstract

The aim of this study is to provide evidence of how a change in the process of calculating the economic valuation of a project can affect the decision regarding national R&D investment. The paper examines a R&D project of cooperative research program of university-industry-research institute for the construction of a woodchip power plant to explore the role of capital expenditure in the economic evaluation of an investment project. The paper finds that the simple introduction of capital expenditure in the profitability analysis affects the perspectives on the construction plan. The results of this study indicate that standardization of the calculation process that takes different characteristics of industries into account is needed in the preliminary feasibility study of national R&D projects.

본 연구는 투자계획의 경제성분석 계산과정의 변화가 어떻게 R&D 투자결정에 영향을 미치는지를 분석하고자 한다. 이를 위해 본 논문에서는 목재칩 발전소 건설의 국가 R&D 산학연협동연구의 투자 계획안 경제성 평가를 위해 자본적 지출의 역할을 탐색한다. 연구 결과 자본적 지출항목을 수익성분석에 포함시키는 것만으로도 건설계획의 투자전망에 영향을 미치는 것으로 나타났다. 본 연구결과는 국가 R&D 과제의 예비타당성 평가에 여러 산업의 특성을 고려한 계산의 표준화가 필요하다는 것을 시사한다.

Keywords

References

  1. An, S., Park, E. and Lee, Y. (2014), "Exploration of Life-cycle Management for Government R&D Program: The Case of Preliminary Feasibility Study on R&D Program", Asian Journal of Innovation and Policy, 17(1): 124-145. (in Korean)
  2. Bae, S. (2009), "An Efficiency Analysis of R&D Investment in Major Cities and Provinces of Korea by Dynamic DEA", Journal of the Korean Regional Economics, 14: 105-129. (in Korean)
  3. Bosch, M-T., Montllor-Serrats, J. and Tarrazon, M-T. (2007), "NPV as a Function of the IRR: The Value Drivers of Investment Projects", Journal of Applied Finance, 17: 41-45.
  4. Cho, Y., Kim, W., Nam, J. and Oh, J. (2005), Policy Directions to Improve the Efficiency of the R&D Investment for Reinforcing the Innovation Capability, Korea Institute for Industrial Economics and Trade. (in Korean)
  5. Coffey, J. E. (2009), "The Capex Adjustment", The value examiner, 10-13.
  6. Dutta, S. and Reichelstein, S. (2012), "Controlling Investment Decisions: Depreciationand Capital Charges", Review of Accounting Studies, 7: 253-281.
  7. Egbide, B., Uwalomwa, U. and Agbude, G. (2013), "Capital Budgeting, Government Policies and the Performance of SMEs in Nigeria: A Hypothetical Case Analysis", IFE PsychologIA, 21(1): 55-73.
  8. Ha, M. (2014), "Factor of Priority Setting in the Government R&D Investment", Journal of Digital Convergence, 12: 1-11.
  9. Harrison, M. (2010), Valuing the Future: The Social Discount Rate in Cost-benefit Analysis, Visiting research paper, Productivity Commission, Canberra, Australia. 1-192.
  10. Jung, U. and Seo, D. W. (2010), "An ANP Approach for R&D Project Evaluation Based on Interdependencies between Research Objectives and Evaluation Criteria", Decision Support Systems, 49: 335-342. https://doi.org/10.1016/j.dss.2010.04.005
  11. Kim, J. and Ha., K. (2013), "A Comparative Study on Government R&D Evaluation System in Selected Countries", Journal of Digital Convergence, 11: 77-90. (in Korean)
  12. Lee, J. (2004), Improving Efficiency of Public R&D System in Korea, Presidential Advisory Council on Science & Technology. (in Korean)
  13. Lee, Y. J. and Yoon, J. (2014), "Analysis of Risk Factors in Ex-ante Evaluation of Large-scale Government R&D Programs", Asian Journal of Innovation and Policy, 17(2): 289-308. (in Korean)
  14. Lee, Y. and Park, J. (2011), "Assessment System for Feasibility Analysis of National R&D Program: The Case of Korea", International Journal of Innovation and Technology Management, 8: 661-676. https://doi.org/10.1142/S0219877011002544
  15. Mellichamp, D. (2013), "New Discounted Cash Flow Method: Estimating Plant Profitability at the Conceptual Design Level While Compensating for Business Risk/uncertainty", Computers and Chemical Engineering, 48: 251-263. https://doi.org/10.1016/j.compchemeng.2012.08.012
  16. Pae, J. and Yoon, S. (2012), "Determinants of Analysts' Cash Flow Forecast Accuracy", Journal of Accounting, Auditing & Finance, 27: 123-144. https://doi.org/10.1177/0148558X11409148
  17. Park, P. and Lee, K. (2009), "A Study on the Government's R&D Budgeting Evaluation System in Korea", Asian Journal of Innovation and Policy, 12(4): 810-839. (in Korean)
  18. Sirilli, G. and Tuzi, F. (2009), "An Evaluation of Government-financed R&D Projects in Italy", Research Evaluation, 18: 163-172. https://doi.org/10.3152/095820209X446092
  19. Sullivan, W. G., Wichs, E. M. and Koelling, C. P. (2012), Engineering Economy, Pearson Education, 200-240.