Evaluation of CM Capability based on Business Functions for International Plant Construction

해외 플랜트 건설사업관리 업무기능별 역량분석

  • Received : 2014.02.06
  • Accepted : 2014.09.11
  • Published : 2014.11.30

Abstract

Ever expanding overseas construction is one of the most important issues for Korean construction companies. Among these issues, strategies for overseas plant construction have widely been discussed, because the plant construction has features of low competitiveness and high ripple effects when compared with other construction sectors. In this sense, the purpose of this research is to evaluate the CM capability of Korean construction industry for overseas plant construction. Fourteen construction business functions and four techniques were defined first. Based on these functions and techniques, CM capability was quantified for As-Is (2013), To-Be (2018) and Gap analyses. Findings of this research reveal that 1) capability for construction is quite competent, 2) capabilities for planning, design management, contracting, and risk management are found to be relatively low, where higher value can be added. In addition, it is found that R&D needs to be extended to develop systemized management techniques. It is also required to secure specialists and original technologies at national industrial level.

국내 건설기업들의 해외 건설시장 진출이 중요한 쟁점이 되고 있는 현 시점에서, 타산업에 비해 경쟁강도가 낮으며, 높은 파급효과를 지닌 플랜트건설 수주확대를 위한 전략모색이 무엇보다 필요하다. 이에 본 연구에서는, 종합적인 측면에서의 표준화된 플랜트건설 사업관리 14가지 업무기능과 4가지 관리기법의 단계적 정의를 바탕으로 플랜트건설 전문가를 대상으로 선진국 대비 현재(2013년)와 미래(2018년)의 사업관리 업무기능별 역량수준을 조사 및 GAP분석을 실시하였다. 그 결과, 과거 실적을 바탕으로 노하우가 축적된 시공관리와 같은 하드웨어적인 역량은 선진국에 비하여 크게 뒤처지지 않으나, 경쟁강도가 상대적으로 낮고 부가가치가 높은 기획, 설계관리, 계약관리, 리스크관리와 같은 소프트웨어적인 측면의 역량은 뒤처진 것으로 나타났다. 또한 국가 산업적 차원에서 전문인력 및 원천기술 확보, 체계적인 관리 지원시스템 구축을 위한 연구개발의 확대가 필요한 것으로 분석되었다.

Keywords

References

  1. Byun, I. W. and Kim, Y. S. (2012). "An Analysis of Core Competence of Pre-construction Service of the Making Inroads into Oversea Construction Market." Korean Journal of Construction Engineering and Management, KICEM, 13(2), pp. 80-90. https://doi.org/10.6106/KJCEM.2012.13.2.080
  2. Choi, S. J., Lee, K. W., and Han, S. H. (2012). "Selection and Strategies of New Leading Businesses in International Construction Market." Korean Journal of Construction Engineering and Management, KICEM, 13(2), pp. 25-36. https://doi.org/10.6106/KJCEM.2012.13.2.025
  3. Construction Economy Research Institute of Korea (CERIK) (2011). Forecasts and Issues of The Domestic and Overaeas Construction Market, CERIK Research Report, 2011-09.
  4. Construction Industry Institute (CII) (1990). Assessment of Construction Contractor Project Management Practices and Performance. CII Special Publication, The University of Texas at Austin, USA, pp. 1-38.
  5. Choi, J. H. and Kim, Y. S. (2013). "An Analysis of Core Competency of Construction Field Engineer for Cost Management." Korean Journal of Construction Engineering and Management, KICEM, 14(5), pp. 26-34. https://doi.org/10.6106/KJCEM.2013.14.5.026
  6. Ha, J. and Jung, Y. (2013a). "Business Functions for Evaluating CM Capability in Plant Construction." Proceedings of AIK Spring Conference 2013, Architectural Institute of Korea, pp. 547-548.
  7. Ha, J. and Jung, Y. (2013b). "CM Capability Base-on Business Functions for Overseas Plant Construction Projects." Proceedings of KICEM Annual Conference 2013, KICEM, 13, pp. 91-92.
  8. Han, J. G. and Park, H. P. (2012). "A Survey on the Perception Level of Technology Competitiveness in Overseas Construction." Proceedings of KICEM Annual Conference 2012, KICEM, 12, pp. 249-250.
  9. Han, J. G., Chin, K. H., and Park, H. P. (2010). "Elicitation Project Management Factors and Evaluation of its Weight to Ensure LNG Plant Success." Proceedings of KIC Scholarship and Technology Conference, The Korea Institute of Building Construction, 10(1), pp. 85-89.
  10. Han, J. G., Park, H. P., and Jang, H. S. (2013). "A Study on Development of the Competitive Evaluation Model in Oversea Construction Industry." Korean Journal of Construction Engineering and Management, KICEM, 14(2), pp. 12-21. https://doi.org/10.6106/KJCEM.2013.14.2.012
  11. Jo, C. H. (2012). "Overseas Construction, Hope of Qualitative Growth Comparable to Quantitative Growth." CERIK Journal, CERIK, 2012-12, pp. 14-16.
  12. Jung, Y. and Gibson, G. E. (1999). "Planning for Computer Integrated Construction." Journal of Computing in Civil Engineering, ASCE, 13(4), pp. 217-225. https://doi.org/10.1061/(ASCE)0887-3801(1999)13:4(217)
  13. Jang, H. S., Lee, B. N., Choi, S. I., and Koo, B. S. (2008). "Competency Assessment of Korean Construction Firms on International Plant Projects." Korean Journal of Construction Engineering and Management, KICEM, 9(4), pp. 173-181.
  14. Jung, Y., Woo, S., Kang, S. H., and Lee, B. N. (2002). "Effects of CM Contracts on the Management Technology in the Korean Construction Industry." Journal of The Korean Society of Civil Enginerring, KSCE, 22(3), pp. 483-495.
  15. Jung, Y., Woo, S., Park, J., Kang, S. H., Lee, Y., and Lee, B. N. (2004). "Evaluation of the Owners' CM Functions." Korean Journal of Construction Engineering and Management, KICEM, 5(3), pp. 128-136.
  16. Jung, Y., Joo, M. and Kim, H. (2011). "Project Management Information Systems for Construction Managers: Current constituents and future extensions", Proceedings of the 28th International Symposium on Automation and Robotics in Construction (ISARC 2011), Seoul, Korea, pp. 597-602.
  17. Kang, K. H., Kim, K. H., Ahn, B. J., and Kim, J. J. (2012). "A Study on the Analysis of Factors of Competence for a Specialist in the International Construction." Journal of the Architectural Institute of Korea, Architectural Institute of Korea, 28(4), pp. 123-131.
  18. Knowledge Industry Information Institute (KNIN) (2013). Market Tendency and Technology Development Strategy for Plant/Engineering Industry. KNIN R&D Information Center, 1st ed, Korea, pp. 49-85.
  19. Korea Institute of Construction Technology (KICT) (2003). Plant Management Procedure. KICT, Korea, pp. 1-3.
  20. Kim, S. S., Kim, J. H., Lee, Y. S., and Kim, J. J. (2007). "A Study on Method Activation of Construction Management through Investigation of Public Owners' Capability level." Proceedings of KICEM Annual Conference 2007, KICEM, 7, pp. 289-294.
  21. Lee, B. N., and Yoo. W. S. (2013). Open Forum to minimize the Potential Risk for Overseas Construction in 2014 : 1st Presentation. September.
  22. Lee, B. N. (2012). "Overseas Construction Expansion - What to do preparation." CERIK Journal, 2012-12, CERIK, pp. 24-27.
  23. LEE, H. i. (2013). "Implication for Construction Companies Through The Characteristics of Maturity Industry and Response Strategies." Construction Issue Focus, 2013-07, CERIK, pp. 1-34.
  24. Ministry of Land, Infrastructure and Transport (MOLIT) (2012). Evaluation and Research of Overseas Construction Execution Capabilities. MOLIT Research Report, Korea, pp. 1-287.
  25. Plant Engineering Plant Technology Center (KEPC) (2012). "Trends of the engineering market in the world." Focus Info, (Jan. 26, 2012).
  26. Project Management Institute (PMI) (2007). Construction Extension to the Project Managmenet Body of Knowledge (PMBOK Guide) Third Edition. PMI, USA, pp. 1-191.
  27. Project Management Institute (PMI) (2013). Project Managmenet Body of Knowledge (PMBOK Guide) Fifth Edition. PMI, USA, pp. 1-415.
  28. Park, H. K., Shin, K. C., Park, H. P., and Jung, Y. (2008). "A Study of the Future Strategy and Mission for the Stakeholders in Industry, Academy, and Government for the Revitalization of CM." Korean Journal of Construction Engineering and Management, KICEM, 9(6), pp. 244-256.
  29. Yoo, S. K., Choi, S. I., and Son, C. B. (2009). "An Analysis of Capability of CM at Risk in Major Construction Company." Korean Journal of Construction Engineering and Management, KICEM, 10(5), pp. 85-94.