Semiconductor Backend Scheduling Using the Backward Pegging

Backward Pegging을 이용한 반도체 후공정 스케줄링

  • Received : 2014.05.13
  • Accepted : 2014.08.12
  • Published : 2014.12.01

Abstract

Presented in this paper is a scheduling method for semiconductor backend process considering the backward pegging. It is known that the pegging for frontend is a process of labeling WIP lots for target order which is specified by due date, quantity, and product specifications including customer information. As a result, it gives the release plan to meet the out target considering current WIP. However, the semiconductor backend process includes the multichip package and test operation for the product bin portion. Therefore, backward pegging method for frontend can't give the release plan for backend process in semiconductor. In this paper, we suggest backward pegging method considering the characteristics of multichip package and test operation in backend process. And we describe the backward pegging problem using the examples.

Keywords

References

  1. Lee, Y.H., Cho, H.M., Park, J.K. and Lee, B.K., 1999, Scheduling Simulator for Semiconductor Fabrication Line, IE Interface, 12(3), pp.437-447.
  2. http://www.ksia.or.kr/renewal/bbs/bbsView.jsp
  3. Kim, Y.-H., Lee, J.-H. and Sun, D.S., 2008, The Operational Optimization of Semiconductor Research and Development Fabs by FAB-wide Scheduling, KIEE International Transactions on Electrical Machinery and Energy Conversion Systems, 57(4), pp.692-699.
  4. Park, D., Yang, J., You, K. and Park, B., Implementation of an E-BOM Copy Method for an Order-specific Semiconductor Equipment, Transactions of the Society of CAD/CAM Engineers, 13(4), pp.273-285.
  5. Lim, S.K., Kim, J.G. and Kang, J.G., 2009, A Collaboration System for Two-stage Semiconductor Manufacturing Supply Chain, Journal of the Korea Management Engineers Society, 14(2), pp.11-29.
  6. Uzsoy, R., Lee, C.Y. and Martin-vega, A.L., 1994, A Review of Production Planning and Scheduling Models in the Semiconductor Industry Part1: System Characteristics, Performance Evaluation and Production Planning, IIE Transactions, 24(4), pp.47-60.
  7. Lee, Y.-H., Kim, S.-Y., Lee, G.-W. and Lee, S.-W., 1995, Production Planning and Control in Semiconductor Industry:Theory and Practice, IE Interfaces, 8(4), pp.73-87.
  8. Lee, Y.-H. and Joung, H.-G., 1990, Development of Seimulator for Efficient Control of Semiconductor Manufacturing Process, International Journal of Production Research, 28(9), pp.1595-1609. https://doi.org/10.1080/00207549008942818
  9. Bang, J.-Y. and Kim, Y.-D., 2011, Scheduling Algorithms for a Semiconductor Probing Facility, Computers & Operations Research, 38(3), pp.666-673. https://doi.org/10.1016/j.cor.2010.08.010
  10. Choi, S.-W., 2012, Scheduling Algorithms for Minimizing Total Weighted Flowtime in Photolithography Workstation of FAB, Journal of the Society of Korea Industrial and Systems Engineering, 35(1), pp.79-86.
  11. Quek, P.T., Gan, B.P., Tan, S.L. and Peng, C.L. 2007, Analysis of the Frontend Wet Strip Efficiency Performance for Productivity. In Proceedings of International Symposium on Semiconductor Manufacturing, ISSM 2007, pp.1-4.
  12. Park, Y.-J., 2008, Minimization of Total Weighted Earliness and Tardiness on a Single Burn-In Oven Using a Genetic Algorithm, Journal of the Society of Korea Industrial and System Engineering, 31(4), pp.21-28.
  13. Park, S.C., Kim, B.H., Seo, J.C., Ahn, E., Chung, Y. and Yang, K.-R., 2013, Fab Simulation with Recipe Arrangement of Tools, Proceedings of the 2013 Winter Simulation Conference.
  14. Rose, O., 2003, Comparison of Due-date Oriented Dispatch Rules in Semiconductor Manufacturing, In Proceeding of the 2003 Industrial Engineering Research Conference.
  15. Zhou, Z. and Rose, O. 2011. A Composite Rule Combining Due Date Control and WIP Balance in a Wafer FAB. In Proceedings of the 2011 Winter Simulation Conference.
  16. GiBrau Mike and Rose, O., 2012, Development and Introduction of a Combined Dispatching Policy at a High-mix Low-volume ASIC Facility, Proceedings of the 2012 Winter Simulation Conference.
  17. Zhou, Z. and Rose, O. 2012. WIP Control and Calibration in a Wafer FAB. In Proceedings of the 2012 Winter Simulation Conference.
  18. Sivakumar, A.I. and Chong, C.S., 2001, A Simulation Based Analysis of Cycle Time Distribution, and Throughput in Semiconductor Backend Manufacturing, Computers in Industry, 45, pp.59-78. https://doi.org/10.1016/S0166-3615(01)00081-1
  19. Chai, J.I., 2008, A Case Study on the Throughput Improvement in the Semiconductor Package Process, Kyung Hee University, Master Degree Thesis.
  20. Quadt, D., Simulation-based Scheduling of Parallel Wire-bonders with Limited Clamp&paddles, Proceedings of the 2006 Winter Simulation Conference.
  21. Tovia, F., Mason, S.J. and Ramasami, B., 2004, A Scheduling Heuristic for Maximizing Wirebonder Thoughput, IEEE Transactions on Electronics Packaging Manufacturing, 27(2).
  22. Jang, S.H., Whang, W.K., Park, S.K., Koh, R.B., Koo, Y.M. and Woo, K.B., 1999 Petri Nets Modeling and Dynamic Scheduling for the Backend Line in Semiconductor Manufacturing, International Journal of Control Robotics and Systems, 5(6), pp.724-733.
  23. Hsu, H.P. and Su, C.T., 2005, The Implementation of an Activity-based Costing Collaborative Planning System for Semiconductor Backend Product, International Journal of Production Research, 43(12), pp.2473-2492. https://doi.org/10.1080/00207540500045824
  24. Weigert, G., Klemmt, A. and Horn, S., 2009, Design and Validation of Heuristic Algorithms for Simulation-based Scheduling of a Semiconductor Backend Facility, International Journal of Production Research, 47(8), pp.2165-2184. https://doi.org/10.1080/00207540902744784
  25. Lu, S.C.H., Ramaswamy, D. and Kumar, P.R., 1998, Efficient Scheduling Policies to Reduce Mean and Variance of Flow-Time in Semiconductor Manufacturing Plants, IEEE Transactions on Semiconductor Manufacturing, 7(3), pp.115-130.
  26. Liu, C., 1992, A Modular Production Planning System for Semiconductor Manufacturing, Ph.D. Dissertation, University of California, Berkeley.
  27. Ko, K., Park, B.C., Yoo, S.K., Park, E.S. and Kim, B.H., 2010, Simulation based FAB Scheduling: SEEPLAN(R). In Proceedings of the 2010 Winter Simulation Conference.
  28. Do, Y.Y., 2013, An Experimental Research on Production rate Improvement of Die Attach Process in Semiconductor Package Manufacturing, Ph.D. Dissertation, Myongji University.