Reinforced-Concrete Works Productivity and Influence Factor Analysis on Nuclear-Power-Plant Project

원자력발전소 건설현장의 철근콘크리트 공종 생산성 및 영향요인 분석

  • Huh, Young-Ki (Department of Architectural Engineering, Pusan National University) ;
  • Lim, Jin-Ho (Department of Architectural Engineering, Pusan National University) ;
  • Kim, Kyoung-Uk (Department of Architectural Engineering, Pusan National University) ;
  • Ahn, Young-Chul (Department of Architectural Engineering, Pusan National University) ;
  • Oh, Jae-Hun (Department of Architectural Engineering, Pusan National University)
  • Received : 2014.02.25
  • Accepted : 2014.05.08
  • Published : 2014.08.20

Abstract

Nuclear power plant projects are being increased all over the world. The construction of nuclear power plants needs huge money and time, which makes conducting a detailed analysis of productivity through the whole process. Reinforced-concrete works productivity field data was collected for more than one year and analyzed from a nuclear-power-plant project in Korea. The productivities of formwork, rebar-work, and concrete pouring were $0.54m^2/man{\cdot}day$, $0.06ton/man{\cdot}day$, $1.98m^3/man{\cdot}day$, respectively. Moreover, it is revealed that 'Day of the Week' is a driver of the formwork activity and 'Overtime' is for all of the three. The results will be a great interest of industry personnel estimating time and cost of a new nuclear power plant.

특수 플랜트 건설은 타 건설사업보다 체계적인 원가 및 공정관리가 요구되지만 이를 위하 반드시 필요한 현장 생산성을 구체적으로 분석한 연구는 이루어지지 않고 있다. 본 연구에서는 국내에서 건설중인 특수 플랜트 현장의 철근콘크리트공종을 형틀, 철근, 콘크리트로 나누어 생산성을 측정하고 생산성에 영향을 미치는 요인을 분석하였다. 생산성 측정결과 형틀공종 $0.54(m^2/man{\cdot}time)$, 철근공종 $0.06(ton/man{\cdot}day)$, 콘크리트공종 $1.98(m^3/man{\cdot}time)$로 나타났다. 영향요인으로는 형틀공종은 요일과 야간적업 유무, 철근공종은 야간잡업 유무, 콘크리트공종은 야간작업 유무와 콘크리트 물량이 통계적으로 유의게 영향을 미치는 것으로 분석되었다.

Keywords

References

  1. Cho YS. Improving Productivity by Effective Construction Management of Atomic Power Station. Journal of the Korea Institute of Construction Management. 2002 Jun;10(2):9-13.
  2. Lee UB, Moon BS. Establishment of Information System for Improving Construction Productivity of Nuclear Power Stations. Journal of the Korea Atomic Industrial Forum. 2000 Dec;214(12):32-8.
  3. Kang HU, Min BJ, Kim YS. A Study on the Influence Analysis of Management list for Overseas Plant Construction Projects Risk Factors. Journal of the Korea Institute of Construction Management. 2010 Nov;261(7): 333-4.
  4. Moon SU, Park SC, Kwon KN. Approximate Estimating of Plant Construction Duration Using a Standard Schedule Model. Journal of the Korea Institute of Construction Management. 2009 Mar;48(2):26-33.
  5. Kim SS, You YH, Cho CY, Son JH. A Study on Measures for Structuring Overseas Plant Database Through the Analysis of Awarded Overseas Plant Orders. Proceeding of the Korea Institute of Construction Management; 2007 Nov 8-9; Busan, Korea. Seoul (Korea): Korea Institute of Construction Management; 2007. p. 234-8.
  6. Koo BH, Kim TH. Application System Improvement of the Codes and Standards for Plant Design. Journal of the Korea Institute of Construction Management. 2007 Aug;38(4):81-9.
  7. Lee SH, Kim SK, Lee JB, Han CH. Proposal for Developed Procurement and Material management System On Using Previous System Analysis in Plant Engineering. Proceeding of the Korea Institute of Construction Management; 2006 Nov 11; Suwon, Korea. Seoul (Korea): Korea Institute of Construction Management; 2006. p. 204-9.
  8. Kim UJ. A Knowledge-based Approach to Plant Construction Process Planning. Journal of the Korea Intelligent Information System Society. 2001 Jun;7(1): 81-95.
  9. Han JG, Chin KH, Park HP. Elicitation Project Management Factors and Evaluation of its Weight to Ensure LNG Plant Success. Proceeding of the Korea Institute of Building Construction; 2010 May 14; Seoul, Korea. Seoul (Korea): Korea Institute of Building Construction; 2010. p. 85-9.
  10. Won SY, Lee JB, Han CH. Analysis of the Pre-construction Process for Overseas LNG Plant Projects. Journal of the Korea Institute of Construction Management. 2009 Dec;38(6):151-9.
  11. Yun SH, Lee SJ, Ock JH. The Analysis of Domestic Plant Engineering Curriculums Based on Architecture Engineering. Proceeding of the Korea Institute of Construction Management; 2011 Nov 11; Seoul, Korea. Seoul (Korea); Korea Institute of Construction Management; 2011. p. 31-4.
  12. Park ES, Jang KS, Koh SW, Lee TS. A Study on Development of Plant Educational Contents For Training the Plant Experts in the Abroad Construction Market. Proceeding of the Korea Institute of Construction Management; 2007 Nov 8-9; Busan, Korea. Seoul (Korea): Korea Institute of Construction Management; 2007. p. 695-8.
  13. Song CB, Hong SH, Lee DU. The Operating Rate of Build Labor of Construction Business Fluctuation and Analysis on Productivity. Journal of the Korea Institute of Architecture. 2010 May;259(5):141-9.
  14. Son JU, Yoon JS, Baek JH. A Study on Construction Productivity Measurement Method. Journal of the Korea Institute of Architecture. 2003 Oct;180(10):101-8.

Cited by

  1. Comparison of Risk Assessment for a Nuclear Power Plant Construction Project Based on Analytic Hierarchy Process and Fuzzy Analytic Hierarchy Process vol.04, pp.03, 2016, https://doi.org/10.4236/jbcpr.2016.43010
  2. Analysis on Risk Factors of Reactor Containment Building Construction using Analytic Hierarchy Process vol.15, pp.4, 2015, https://doi.org/10.5345/JKIBC.2015.15.4.425
  3. Evaluation of Construction RCB Exterior Wall Formwork according to Placing Height on Nuclear Power Plant vol.15, pp.6, 2015, https://doi.org/10.5345/JKIBC.2015.15.6.653