Development of Hierarchical Checking Tables for Safety Management of Apartment Gang-form Works

  • Kang, Jung-Woo (GS Engineering & Construction Corp.) ;
  • Cho, Dong-Hyun (Department of Architectural Engineering, The University of Seoul) ;
  • Koo, Kyo-Jin (Department of Architectural Engineering, The University of Seoul)
  • Received : 2013.03.18
  • Accepted : 2013.10.18
  • Published : 2014.04.20

Abstract

The gang-form widely used in apartment construction sites has advantages compared to scaffolding in preventing falling accidents. One problem, however, is that safety accidents associated with gang-form works repeatedly occur due to worker carelessness. In this study, hierarchical checking tables are provided to support safety management activities for the gang-form works at the sites. Through a survey of experts and analyses of case studies of construction accidents, 137 safety check items are classified by participant type based on a hierarchical safety check scheme. The applicability and effectiveness of the hierarchical checking tables was evaluated through interviews with experts. It was found that the hierarchical checking tables enabled each gang-form related participant to check his own safety management items, and provided a level-wise structure to site safety management systems.

Keywords

References

  1. Lee JH, Yang SH, Kim YS. Development of an automated gangform climbing system for apartment housing construction: structural stability and tower crane lifting load analysis. Korean Journal of Construction Engineering and Management. 2012 Jul;13(4):48-59. https://doi.org/10.6106/KJCEM.2012.13.4.048
  2. Huang RY, Sun KS, Chen JJ. Construction planning for gang formwork reuse using simulation. Proceedings of the 17th International Symposium on Automation and Robotics in Construction; 2000 Sep 18-20;Taipei, Taiwan. Taipei (Taiwan): The International Association for Automation and Robotics in Construction; 2000. p. 1153-61.
  3. Shin HW, Kim GH, Kim JY, Cho HK. A research on a comparison between the strength and weakness of each formwork methods in the core wall construction. Journal of the Korea Institute of Building Construction. 2007 Dec; 7(4):153-9. https://doi.org/10.5345/JKIC.2007.7.4.153
  4. Peurifoy RL, Oberlender GD. Formwork for concrete structures. 4th ed. New York: McGraw-Hill; 2011. 518 p.
  5. Kim GH, Kang KI. A study on development and application of the unit table form for concrete structural frame work of high-rise buildings. Journal of the Architectural Institute of Korea. 2003 Aug;19(8):181-8.
  6. Choudhry RM, Fang DP, Ahmed SM. Safety management in construction: best practices in Hong Kong. Journal of Professional Issues in Engineering Education & Practice. 2008 Jan;134(1):20-32. https://doi.org/10.1061/(ASCE)1052-3928(2008)134:1(20)
  7. Lee HC, Yeo SK, Go SS. A study on the improving safety management by analyzing safety consciousness of construction labors. Journal of the Korea Institute of Building Construction. 2009 Jun;9(3):51-8. https://doi.org/10.5345/JKIC.2009.9.3.051
  8. Ahn HS. A study on the improvement of the safety organizations for construction projects. Journal of the Architectural Institute of Korea. 2005 Sep;21(9):137-44.
  9. Abdelhamid TS, Everett JG. Identifying root causes of construction accidents. Journal of Construction Engineering and Management. 2000 Jan;126(1):52-60. https://doi.org/10.1061/(ASCE)0733-9364(2000)126:1(52)
  10. An, SH, Ryu HW, Park MS. Selecting key accident risk factors in building construction projects. Journal Of the Korea Institute of Building Construction. 2011 Feb;11(1): 45-50. https://doi.org/10.5345/JKIC.2011.02.1.045
  11. Son CB, Kim BL. Improvement of the field management work and operation system in the apartment construction. Journal of the Architectural Institute of Korea. 2006 Jun; 22(6):165-72.
  12. Fang DP, Huang XY, Hinze J. Benchmarking studies on construction safety management in China. Journal of Construction Engineering and Management. 2004 Jun;130(3): 424-32. https://doi.org/10.1061/(ASCE)0733-9364(2004)130:3(424)
  13. Yi KJ. Proactive safety planning model by integrating hazard risk and work schedule. Journal of the Architectural Institute of Korea. 2004 Apr;20(4):109-16.
  14. Lee HS, Lee KP, Park MS, Baek YJ, Lee SH. RFID-based real-time locating system for construction safety management. Journal of Computing in Civil Engineering. 2012 May;26(3): 366-77. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000144
  15. Jia N, Xie M, Chai X. Development and implementation of a GIS-based safety monitoring system for hydropower station construction. Journal of Computing in Civil Engineering. 2012 Jan;26(1):44-53. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000105
  16. Hallowell MR, Gambatese JA. Activity-based safety risk quantification for concrete formwork construction. Journal of Construction Engineering and Management. 2009 Oct; 135(10):990-8. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000071
  17. Moon S, Choi B, Yang B. USN-based data acquisition for increasing safety in the concrete formwork operation. Journal of Computing in Civil Engineering. 2012 May;26(3):271-81. https://doi.org/10.1061/(ASCE)CP.1943-5487.0000132
  18. Yang YC, Choi H, Kim JJ. A study of methods on safety checklist improvement and integrated operation with schedule for construction accident prevention. Korean Journal of Construction Engineering and Management. 2004 Apr;5(2): 123-35.
  19. Shim UJ, Suh HS, Ahn YS. Highly efficient checklist for the safety management of reinforced concrete construction. Journal of the Korea Institute of Building Construction. 2010 Dec;10(6):7-17. https://doi.org/10.5345/JKIC.2010.12.6.007
  20. Kim JR, Yoon SY, Cho YJ. Hands-on tools to prevent human errors in highway construction. Journal of the Ergonomics Society of Korea. 2011 Feb;30(1):19-28 https://doi.org/10.5143/JESK.2011.30.1.19
  21. Lee KT. Analysis of causes and the precautionary measures on disaster caused by the collapse of the gang form. Incheon (Korea): the Occupational Safety and Health Research Institute; 2005 Dec. Report No.: 2005-82-544. 31 p.