Effect of Inadequate Design on Cost and Time Overrun of Road Construction Projects in Tanzania

  • Rwakarehe, Eradius E. (Department of Transportation and Geotechnical Engineering, University of Dar es Salaam) ;
  • Mfinanga, David A. (Department of Transportation and Geotechnical Engineering, University of Dar es Salaam)
  • Received : 2013.01.10
  • Accepted : 2013.09.24
  • Published : 2014.03.01

Abstract

Completing road construction projects within the budget and time has been a problem for the Tanzania National Roads Agency (TANROADS); and the major problem highlighted in almost all projects being inadequate design. However, the extent to which inadequate design contributes to both time and cost overruns and its causes remained under-studied. The objective of this study is therefore to determine the extent of the effect of inadequate design, its causes and remedial measures. The methodology used in this study includes reviewing recent projects completion reports, holding roundtable discussions with consultants and TANROADS officials and analyzing the information. Cost and time overruns for the reviewed projects averaged 44% and 26% respectively. Similarly, the extents to which inadequate design contributes to cost and time overruns were on average found to be 61% and 85% respectively. The overruns are predominantly related to problems that occurred during the design process. To alleviate the problem, TANROADS is advised to improve the management of design projects, enhance the process of reviewing design reports, improve the design process including introducing Road Safety Audit and geometric design manuals, and increase staff to match the work-load.

Keywords

References

  1. M. Emhjellen, K. Emhjellen, P. Osmundsen, "Cost Estimation Overruns in the North Sea", Project Management Journal, PMI vol. 34, no. 1, pp. 23-29, 2003.
  2. H. Chandra, "Management of construction in developing countries: Indian experience", Proceedings of CIB 90 Joint Symposium on Building Economics and Construction Management, Sydney, Australia, vol.5, pp. 211-224, 1990.
  3. S. Morris, "Cost and Time Overruns in Public Sector Projects", Economic and Political Weekly, vol. 25, no. 47, pp. 154-168, 1990.
  4. A.S. Chang, "Reasons for Cost and Schedule Increase for Engineering Design Projects", Journal of Management in Engineering, ASCE, vol. 18, no.1, pp. 29-36, 2002.
  5. R. Mendelsohn, "The Constructability Review Process: A Constructor's Perspective", Journal of Management in Engineering, ASCE, vol. 13, no. 3, pp. 17-19, 1997.
  6. S.D. Anderson, D.J. Fisher, S.P. Rahman, "Constructability Issues for Highway Projects", Journal of Management in Engineering, ASCE, vol. 15, no.3, pp. 60-68, 1999.
  7. G. Creedy, M. Skitmore, J. Wong, "Evaluation of Risk Factors Leading to Cost Overrun in Delivery of Highway Construction Projects", Journal of Construction Engineering and Management, vol. 136, no.5, pp. 528-537, 2010. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000160
  8. R. Apolot, H. Alinaitwe, D. Tindiwensi, "An Investigation into the Causes of Delay and Cost Overrun in Uganda's Public Sector Construction Projects", Proceedings of 2nd International Conference on Advances in Engineering and Technology, Entebe, pp. 305-312, 2011.
  9. S.M. Vidalis, F.T. Najafi, "Cost and Time Overruns in Highway Construction", Proceedings of 4th Transportation Specialty Conference of the Canadian Society for Civil Engineering, Montreal, Quebec, 2002.
  10. C. Kaliba, M. Muya, K. Mumba, "Cost Escalation and Schedule Delay in Road Construction Projects in Zambia", International Journal of Project Management, vol. 27, no. 5, pp.522-531, 2009. https://doi.org/10.1016/j.ijproman.2008.07.003
  11. Ireland's National Roads Authority, "Project Development for Ireland roads", Publications Unit, National Roads Authority, Dublin, 2008.
  12. European Transport Safety Council, "Road Safety Audit and Safety Impact Assessment", Rue du Cornet, Brussels, 1997.
  13. J. Wrisberg, P.K. Nilsson, "Safety audit in Denmark-a cost-effective Activity", Danish Road Directorate, Copenhagen, 1996.
  14. A. Arnitis, D. Sevele, M. Nauzere, "Technology of Feasibility Study", Strategy Development, Latvian State Roads, Riga, 2005.
  15. Oregon Department of Transportation, "Road Design Manual", ODoT, Oregon, 2000.
  16. Montana Department of Transport, "Road Design Manual", Montana Department of Transport, Montana, 2008.
  17. Vermont Agency of Transportation, "Highway Project Development Process", Vermont Agency of Transportation, Montpelier, 2008.
  18. C.A.O'Flaherty, "Highways: The Location, Design, Construction & Maintenance of Pavements", Butterworth-Heinemann, Malta, 2002.
  19. B. Flyvbjerg, M.S. Holm, S. Buhl, "Underestimating Costs in Public Works Projects: Error or Lie?", Journal of the American Planning Association, APA, vol. 68, no.3, pp. 279-295, 2002. https://doi.org/10.1080/01944360208976273
  20. K.C. Sinha, C. Bordat, B.G. McCullouch, S. Labi, "An Analysis of Cost Overruns and Time Delays of INDOT Projects", Publication FHWA/IN/JTRP-2004/07, Joint Transportation Research Program, Indiana Department of Transportation and Purdue University, West Lafayette, Indiana, 2004.
  21. TANROADS, "Mutukula-Muhutwe Road Upgrading Project, Project Completion Report", TANROADS, Dar es Salaam, 2006a.
  22. TANROADS, "Shelui-Nzega Road Upgrading Project, Project Completion Report", TANROADS, Dar es Salaam, 2006b.
  23. TANROADS, "Nzega-Isaka (Via Tinde) Road Upgrading Project 73km: Final Report", TANROADS, Dar es Salaam, 2007.
  24. TANROADS, "Mwanza/Shinyanga Border-Tinde Road Upgrading Project: Project Completion Report", TANROADS, Dar es Salaam, 2008a.
  25. TANROADS, "Singida-Shelui Road Upgrading (Package 1: Singida Town-Iguguno), Project Completion Report", TANROADS, Dar es Salaam, 2008b.
  26. TANROADS, "Singida-Shelui Road Upgrading (Package 2: Iguguno-Sekenke Diversion), Project Completion Report", TANROADS, Dar es Salaam, 2008c.
  27. TANROADS, "Singida-Shelui Road Upgrading (Package 3: Sekenke Diversion-Shelui), Project Completion Report", TANROADS, Dar es Salaam, 2008d.
  28. J. K. Hollmann, L. R. Dysert, "Escalation Estimation: Working With Economics Consultants", AACE International Transactions, AACE International, 2007.

Cited by

  1. Modeling schedule overrun and cost escalation percentages of highway projects using fuzzy approach vol.24, pp.5, 2017, https://doi.org/10.1108/ECAM-03-2016-0084