Abstract
Economic feasibility study using weighted average variable Jeju System Marginal Price, SMP, was conducted for Gasiri wind farm of Jeju Island. To predict the variable Jeju SMP, generator share ratio for SMP was calculated from the real time wind power production and the power demand data for years. Also, sensitivity analysis on Net Present Value, NPV, and Benefit/Cost Ratio, B/C ratio, were performed to clarify which factors are more important in assessing economic feasibility. The result shows that the Gasiri wind farm has a minimum of 110 billion won and a maximum of 132 billion won difference between fixed and variable SMP. Also, Capacity Factor, C.F., had the highest sensitivity for NPV, followed by SMP. Accordingly, when economic analysis for a potential wind farm site is carried out, the variable SMP as well as C.F. should be considered for more accurate assessment of the wind farm.