Abstract
In this study, the hydraulic channel routing model was constructed to analysis the effect of flood control with the operation of Chungju Dam for 2006 flood. Study area was divided with up- and downstream of Chungju Dam in the upper Han River of Paldang Dam. The model was calibrated and verified for the flood event of 1995-2008. The effects of flood control of Chungju Dam were compared with the simulation results without the dam, and the rising effects of stage in the main observation stations were analyzed by the variation of released dam discharge. Consequently, the operation of Chungju Dam for 2006 flood was performed properly, but the effects of flood control of Chungju Dam were so focused in downstream of the dam that institutional complement was demanded to reduce the flood damage in the upper region of the dam. The limit of decision rule of downstream stage in the backwater region of dam was analyzed to solve the problem, and the decision rule of downstream stage was proposed to consider the discontinuity between the backwater region of dam and the design flood of upper stream. The proposed rule will be used to design the reduction of flood damage in upper stream of dam and to apply the analysis of region for flood damage.
본 연구에서는 2006년 홍수시 충주댐 운영에 따른 댐 상 하류의 홍수위 상승영향을 정량적으로 분석하기 위하여 팔당댐 상류의 한강 본류에 위치한 충주댐을 기준으로 상류구간과 하류구간으로 구분하고, 1995년부터 2008년까지의 홍수사상을 대상으로 모형을 검보정함으로써 수리학적 모형을 구축하였다. 구축된 모형을 이용하여 충주댐의 유무를 가정하여 충주댐의 홍수조절효과를 검토하고, 방류량의 변화에 따른 상 하류 주요지점의 수위 상승영향을 정량적으로 분석하였다. 분석결과, 2006년 홍수시 충주댐의 운영이 비교적 적절하게 수행되었음을 확인하였으나, 충주댐의 홍수조절효과는 댐 하류구간에 집중되어 있어 댐 상류 홍수피해 저감을 위한 제도적 보완이 필요한 것으로 분석되었다. 이러한 문제점을 해결하기 위하여 기존 댐 배수구간 상류 하천의 기점수위 결정방법의 한계를 검토하였으며, 댐 배수구간과 상류 하천의 계획홍수량 불연속을 반영할 수 있는 기점수위 결정방법을 제안하였다. 제안된 방법은 댐 상류하천의 홍수피해 저감을 위한 설계 및 홍수피해 발생시 피해원인 분석에 활용될 수 있을 것이다.