Abstract
The risk of pipe-bursting in multi-regional transmission mains consisting of 89 % of singled pipeline is so high that pipeline stabilization project is required such as renewal and replacement, pipe paralleling, emergency ties. Pipeline stabilization projects could be postponed at the step of initial decision-making because effect of this project is intangible benefit like activation of economic, improvement of welfare related to water. This study is to suggest quantified economical feasibility model for intangible benefit presumption to solve above problem. Cost reduction of emergency water supply, leakage, burst restore and energy efficiency improvement was altered and applied. As a result of economic analysis taking into account estimated benefit and cost under discount rate 5.5 %, service life 40 years, sufficient economic feasibility analyzed with B/C 2.45, NPV 317,700 million won, IRR 9.09 %.