Analysis of effect on power system considering the maximum penetration limit of wind power

풍력발전 한계운전용량에 대한 계통영향 분석

  • Myung, Ho-San (Multidisciplinary Graduate School Program For Wind Energy, Jeju National University) ;
  • Kim, Bong-Eon (Multidisciplinary Graduate School Program For Wind Energy, Jeju National University) ;
  • Kim, Hyeong-Taek (Multidisciplinary Graduate School Program For Wind Energy, Jeju National University) ;
  • Kim, Se-Ho (Faculty of Electrical Eng., Jeju National University)
  • 명호산 (제주대학교 풍력특성화협동과정) ;
  • 김봉언 (제주대학교 풍력특성화협동과정) ;
  • 김형택 (제주대학교 풍력특성화협동과정) ;
  • 김세호 (제주대학교 전기공학과)
  • Received : 2012.04.04
  • Accepted : 2012.06.14
  • Published : 2012.06.30

Abstract

About supply and demand to see that you need to match, the limitations of wind power capacity is low demand and the commitment of the general generator will exist between the minimum generation. if the turbine's output can be controlled, The limitation of wind power capacity will be adopted based on instant power generation. Namely, The minimum limits of wind power generation based load operation by calculating the amount that is higher than if the output should be restricted to highest operation. in this paper, we committed to the demand for low enough that the combination of the general generator of wind power capacity to accommodate the operation of determining whether the limit is intended to. For this, power system analysis program PSS/E was used, Jeju system by implementing the model simulations were performed.

Keywords

References

  1. E.A. Demeo. W. Grant, "Wind Plant Integration Costs, Status, and Issuses", IEEE power & energy, 12. 2005
  2. Holttinen and R. Hirvonen. "Power System Requirements for Wind Power." (Wind Power in Power Systems, T. Ackermann, Ed. John Wiley & Sons, 2005, pp.143-167.)
  3. KEPCO, "Research on the Maximum Penetration Limit of Wind Power and the Operation Scheme of the Jeju Power System" (Final report), 2008. 7.
  4. KPX, "A Study on the Operating Reserve for Jeju power system" (Final report), 2011. 4.
  5. MKE, The 5th Electricity Supply and Demand Plan, 2010.
  6. PTI, PSS/E User Manual, version 32, June 2009