Discrete Event Simulation for the Initial Capacity Estimation of Shipyard Based on the Master Production Schedule

대일정 생산 계획에 따른 조선소 생산 용량의 초기 평가를 위한 이산사건 시뮬레이션

  • Kim, Kwang-Sik (Dept. of Naval Architecture and Ocean Engineering, INHA University) ;
  • Hwang, Ho-Jin (MOERI(Maritime and Ocean Engineering Research Institute), KORDI) ;
  • Lee, Jang-Hyun (Dept. of Naval Architecture and Ocean Engineering, INHA University)
  • 김광식 (인하대학교 조선해양공학과) ;
  • 황호진 (한국해양연구원 대덕분원) ;
  • 이장현 (인하대학교 조선해양공학과)
  • Received : 2011.12.21
  • Accepted : 2012.03.05
  • Published : 2012.04.01

Abstract

Capacity planning plays an important role not only for master production plan but also for facility or layout design in shipbuilding. Product work breakdown structure, attributes of production resources, and production method or process data are associated in order to make the discrete event simulation model of shipyard layout plan. The production amount of each process and the process time is assumed to be stochastic. Based on the stochastic discrete event simulation model, the production capacity of each facility in shipyard is estimated. The stochastic model of product arrival time, process time and transferring time is introduced for each process. Also, the production capacity is estimated for the assumed master production schedule.

Keywords

References

  1. Song, Y. J., Lee, D. K., Choe, S. W., Woo, J. H. and Shin, J. G., 2009, A Simulation-Based Capacity Analysis of a Block-Assembly Process in Ship Production Planning, Journal of the Society of Naval Architects of Korea, 46(1), pp. 78-86. https://doi.org/10.3744/SNAK.2009.46.1.078
  2. Chabane, H., 2004, Design of a Small Shipyard Facility Layout Optimised for Production and Repair, Symposium International: Qualite et Maintenance au Service de I'Enterprise QUALIMA01- Tlemecen.
  3. Shin, J. G., Lee, J. H. and Woo, J. H., 2001, Digital Shipbuilding, Bulletin of the Society of Naval Architects of Korea, 38(1), pp. 54-61.
  4. Woo, J. H., Oh, D. K., Lee, C. J., Choi, Y. R. and Shin, J. G., 2006, Simulation Modeling Methodology and Simulation System Architecture for Shipbuilding Processes, Transactions of the Society of CAD/CAM Engineers, 11(1), pp. 11-19.
  5. Lee, C. J., Lee, J. H., Woo, J. H., Shin, J. G. and Ryu, C. H., 2007, A Study on Discrete Event Simulation of Shipyard Outdoor Block Movement, Journal of the Society of Naval Architects of Korea, 44(6), pp. 647-656. https://doi.org/10.3744/SNAK.2007.44.6.647
  6. NedeB, C., Friedewald, A., Wanger, L. and Hubler, M., 2006, Simulation of material flow processes in the planning of production spaces on shipbuilding, The 5th International Conference on Computer Applications.
  7. Dain, O. and Pardoe, I., 2006, Stochastic shipyard simulation with SIMYARD, Proceeding of 2006 Winter Simulation Conference, Monterey, CA, USA, pp. 1770-1778.
  8. Yoon, T. H., Lee, H. Y. and Kang, Y. W., 2009, An application of Digital Virtual Factory and Process Simulation for Shipbuilding Assembly shop, Proceedings of the Society of CAD/CAM Conference, PyeongChang, Korea, pp.475-481.
  9. Park, J. H., 2006, A Study on Shipyard Layout Arrangement by Estimation of Production Capacity, Master Thesis, INHA University.
  10. HHI(Hyundai Heavy Industry), 1991, Manufacturing System of Shipbuilding - Automation System for Cutting, Forming and Assembly Process, Ministry of Science and Technology, Korea.

Cited by

  1. The Integrated Design and Analysis of Manufacturing Lines (I) - an Automated Modeling & Simulation System for Digital Virtual Manufacturing vol.19, pp.2, 2014, https://doi.org/10.7315/CADCAM.2014.138
  2. The Integrated Design and Analysis of Manufacturing Lines (II) - Continuous Design, Analysis and Optimization through Digital Virtual Manufacturing vol.19, pp.2, 2014, https://doi.org/10.7315/CADCAM.2014.148
  3. Quality Verification of Legacy Data of Manufacturing Information System to Improve Results of Shipyard Manufacturing Logistics Simulation vol.51, pp.6, 2014, https://doi.org/10.3744/SNAK.2014.51.6.510