논문 - 수리시설물의 적정개보수 주기 및 비용 산정

Assessment of Appropriate Period and Cost(P&C) of Repair and Improvement for Irrigational Structures

  • 이준구 (한국농어촌공사 농어촌연구원) ;
  • 김명원 (한국농어촌공사 농어촌연구원) ;
  • 신태호 (한국농어촌공사 농어촌연구원)
  • 발행 : 2011.12.30

초록

This study was performed to apply the preventive management technique that is known for more economic and preventive for disaster than corrective technique to Repair & Improvement(R&I) Project policy of irrigational facilities. The appropriate periods of R&I Project had been driven to 40yrs, 24yrs, 27yrs, and 29yrs for reservoir, Pumping and drainage pumping station, Diversion weir and Irrigation & drainage canal respectively. The cost of R&I Project for 10 years had been estimated as 616.9 billion won per year including the 85 billion won for the project of 'Disaster prevention and Function continuity'. After the period of 'Improvement all at once', about 30yrs, 421.8 billion won was requested for 'Function continuity'.

키워드

과제정보

연구 과제번호 : 수리시설물의 적정개보수주기 및 비용 산정

연구 과제 주관 기관 : 농림부