Abstract
This study represents construction progress management model based on quality inspection process in addition to cost-schedule integration. Quality inspection process cycle, resource estimate as progress measurement parameter, hierarchical structure of schedule, and inspection lots linking quality inspection to resource estimate are addressed as four main information areas. The authors established several process models to give a structure and correlations among information elements on each of these areas. Applying the process models proposed, an information system was implemented and utilized for nuclear power plant construction. It reveals that the system achieves accurate and objective progress information in near real time with significantly reduced time and effort as well as administrative efficiencies from making quality inspection process online.
본 연구에서는 일정-비용 통합모델 기반의 공사 진척도 관리에 있어서 현장작업에 대한 품질검사 프로세스를 연계한 진척도 측정모델을 제시하였다. 이를 위해 1)품질검사 프로세스, 2)진척도 측정매개, 3)계층구조화된 공정표, 4)진척도 측정매개와 연계된 품질검사 대상의 네 가지를 모델의 핵심영역으로 정의하고, 각 영역에 대한 정보요소들을 분석하였다. 그 결과를 토대로 각 영역 간에 서로 연관성을 가지고 품질검사의 계획과 실행 결과가 진척도 측정에 활용될 수 있도록 정보요소들을 구성하는 프로세스 모델들을 제시하였으며, 이를 반영한 정보시스템을 구현하여 원자력 발전소 건설공사에 적용하였다. 시스템 운영을 통한 모델의 효용성을 검증한 결과, 품질검사 프로세스의 온라인화를 통한 정보소통의 효율성 향상 및 기존 오프라인 방식에서 발생하던 현장 간접경비의 절감효과 뿐만 아니라, 발주자와 계약자가 모두 인정할 수 있는 객관적인 진척도 정보를 신속하게 획득할 수 있는 효과가 있는 것으로 확인되었다.