Development of a Risk Management Procedure Model for the Construction Project Using Construction Risk Management System

CRMS를 활용한 건설공사의 리스크관리 절차모형 개발

  • 김창학 (진주산업대학교 토목공학과) ;
  • 강인석 (경상대학교 토목공학과 공학연구원) ;
  • 박홍태 (공주대학교 건설환경공학부)
  • Received : 2010.03.25
  • Accepted : 2010.05.11
  • Published : 2010.08.31

Abstract

This study suggested CRMS (construction risk management system) which is a new risk analysis model after analyzing existing risk management process for to guarantee a successful performance at the construction planning and work phase. CRMS is risk management procedures in order that the contractor identify, analyze and administrate the risk during performing construction project. This model may give much help to quantify and be ready the right managing methods about identified risk by the contractor. Especially, the most important and difficult things of all risk management may be to identify risk in the project. This study make more focusing on the developing a procedure that can identify risk more easily in the construction project. The risk is divided into global risk and local risk of a project. Also, this study suggests methods which are using the RBS (risk breakdown structure) related with WBS. This result will be useful as basic materials for developing computerizing system for risk management.

본 연구에서는 공사기획단계와 시공단계에서 공사의 성공적 이행을 보장하기 위해 기존의 리스크관리 프로세스를 살펴보고 이에 적합한 새로운 리스크분석 모델인 CRMS를 제시한다. CRMS는 시공자가 건설공사의 이행중 리스크를 확인하고, 분석하고, 관리해 가기 위한 리스크관리절차이다. 이것은 시공자가 인지한 리스크를 정량화하고 이에 적절한 리스크관리 방안을 수립하는데 큰 도움을 줄 수 있다. 특히 건설공사의 리스크관리 중 가장 중요하고 어려운 부문이 리스크를 인지하는 것으로 볼 수 있다. 따라서 본 연구에서는 건설공사의 리스크인지를 쉽게 할 수 있는 절차의 개발에 좀 더 집중하였다. 리스크의 확인은 프로젝트의 외적 리스크와 내적 리스크로 구분한다. 글로벌 리스크의 경우 확인을 용이하게 하기 위해 분석에 필요한 목록을 제시하고, 아울러 RBS의 구축방법과 WBS와의 연계방안을 제시하였다. 이러한 연구결과는 리스크관리용 전산시스템을 개발하기 위한 기초자료로 활용되게 될 것이다.

Keywords

References

  1. 강인석, 김창학, 이우식(2002) 건설공사 리스크 할당도분석을 통한 계약자간 리스크 인자확인 연구, 대한토목학회논문집, 대한토목학회, 제22권 제1D호, pp. 81-91.
  2. 김창학, 박서영, 강인석(2006) 건설공사의 리스크관리를 위한 통합전산모형 구축, 대한토목학회논문집, 대한토목학회, 제26권 제3D호, pp. 469-480
  3. 김창학, 박서영, 강인석(2002) 대형건설공사 위험인자의 중요도판정을 위한 퍼지 평가모형 적용성 연구, 대한토목학회논문집, 대한토목학회, 제22권 제5D호, pp. 923-933.
  4. 김창학, 강인석, 박홍태(2000) 대형 건설공사의 기획단계 리스크 지수 산정에 관한 연구, 대한토목학회논문집, 대한토목학회, 제20권 제5D호, pp. 559-569.
  5. 해외건설협회, 해외건설공사 통합 리스크관리시스템, http://rms.icak.or.kr/
  6. Abrahamson, M.W. (1973) Construction Risk in Tunnelling How They Should Be Shared, Tunnels and Tunneling, pp. 587-598.
  7. Al-Bahar, J.F. (1988) Risk Management Approach for Construction Project: A Systematic Analytical Approach for Contractors, Ph. D. Thesis.
  8. Al-Bahar, J.F. and Crandall, K.C. (1990) Systematic risk management approach for construction., Journal of Construction Engineering and Management, ASCE, Vol. 116, No. 3, pp. 533-546. https://doi.org/10.1061/(ASCE)0733-9364(1990)116:3(533)
  9. Aleshin, A. and Dworatschek, S. (1997) Risk management of joint venture construction projects of foreign cooperation in russia, PMI 28th Annual Seminars & Symposium, pp. 221-226.
  10. Ashley, D.B. (1988) Impact of Risk Allocation and Equity in Construction Contracts, CII.
  11. Baldwin, J.R., Manthei, J.M., Routhbart, H., and Horns, R.B. (1971) Causes of delay in the construction industry, Journal of the Construction Division, ASCE, pp. 105-106.
  12. Jaafari, A. (1994) Total project risk management aided by information systems, 12th INTERNET World Congress on Project Management, Proceedings, Vol. 2, pp. 311-317.
  13. Mason, G.E. (1973) A Quantitative Risk Management Approach to the Selection of Construction Contract Provision, Technical Report, Stanford University.
  14. Mootanah, D.P. (1997) A holistic framework for managing risks in construction projects, PMI 28th Annual Seminars & Symposium, pp. 1056-1062.
  15. Perry, J.G. and Hayes, R.W. (1985) Hayes, risk and its management in construction projects, Proceeding of the Institution of Civil Engineers, Thomas Telford Ltd., pp. 499-521.
  16. Smith, M.A. (1996) Understanding Construction Risks, Construction Insurance, Bonding, and Risk Management, McGraw-Hill, pp. 9-21.
  17. Wideman, R.M. (1986) Risk management project, Management Journal, pp. 20-26.
  18. Zhi, H. (1995) Risk management for overseas construction projects, International Journal of Project Management, Vol. 13, No. 4, pp. 231-237. https://doi.org/10.1016/0263-7863(95)00015-I