The long-term operating evaluation of the grid connected photovoltaic system

중규모 태양광발전시스템 장기 실증운전 평가

  • Published : 2009.10.30

Abstract

The 50 kWp grid connected photovoltaic system which was installed at KEPRI site in 1999 has been operated more than 10 years. In order to acquire long term operation characteristics of medium size photovoltaic system, the operation test data related on power generation electricity and capacity factor of 50 kWp system, which have been collected since 1999, were analysed. From the analysing results, 57.7 MWh in annual power generation electricity of 50 kWp photovoltaic system in 1999 has been decreased 49.1 MWh in 2005 and reached 41.9 MWh in 2008. In addition to, the capacity factor of 50 kWp photovoltaic system also showed 13.2 % in 1999, 11.2% in 2005 and finally reached 9.6% in 2008. The operation test data showed a trend of decreasing of generation electricity and capacity factor during the 10 years operation time and we guessed that was caused by solar cell performance degradation and decreasing of PCS system efficiency.

Keywords

References

  1. Electric Power Research Institute, AP 3351 : Photovoltaic Power Systems Research Evaluation : A Report of the EPRI Ad Hoc Photovoltaic Advisory committee, Prepared by Strategies Unlimited, EPRI, Palo Alto, CA, 1983, p. C-5
  2. U. S. Department of Energy, National Photovoltaic Program : Five Year Research Plan, 1987-1991, U. S. DOE, Washington DC, 1987, p. 26
  3. 한국 전력공사, '50kWp급 계통연계형 태양광 발전시스템 개발 최종보고서', 1999
  4. 산업자원부, '주택용 태양광 발전시스템의 운전평가 및 실용보급방안 연구 최종보고서', 2003
  5. 분산형 전원의 배전계통 연계기술 기준, 한국전력 공사, 2005