Abstract

The pipe jacking method which is a non-excavation method is frequently used due to constructability and economical efficiency in a medium or small-sized pipeline construction. However, jacking process of the method still causes problems that the base ground is disturbed and loosen. These lead to surface settlement, strength decrease and leakage of water. Therefore, this study presents in-situ application of the steel pipe jacking with grouting, and it is that jacking and grouting are progressed simultaneously. To verify this, the steel pipe jacking with grouting and the existing steel pipe jacking have been constructed on the same ground condition. It has been proved that the steel pipe jacking with grouting is in-situ applicable according to results of monitoring surface settlement, in-situ density, GPR geophysical prospecting and large scale direct shear test.

강관추진공법은 비굴착공법으로써 중소규모 관로공사에 높은 시공성과 경제성을 가지고 있기 때문에 그 사용이 빈번해지고 있다. 그러나 강관추진공법의 추진과정은 원지반이 교란되고 느슨해지는 문제를 야기하고 있다. 이는 지표침하, 지반강도 저하 및 누수 등의 문제와 연결된다. 이에 본 연구는 강관추진과 동시에 그라우팅을 시행하는 그라우팅을 병행한 강관추진공법의 현장 적용성을 알아보고자 한다. 그 방법으로 그라우팅을 병행한 강관추진공법과 기존강관추진공법을 동일 지반에 시공하였다. 지표침하 계측, 현장밀도, GPR 물리탐사 그리고 대형전단실험의 결과는 그라우팅을 병행한 강관추진공법의 현장 적용성이 있음을 입증하였다.

Keywords

References

  1. 박현수, "강관압입공법의 설계 및 시공에 관한 사례연구, 순천대학교 산업대학원, 2003
  2. 高恨昇, '推進工法', 森北出版, 1982
  3. Hideki Shimada, Saeid Khazaei, Kikuo Matsui, "Small diameter tunnel excavation method using slurry pipe-jacking", Geotechnical and Geological Engineering 22, 2004, pp. 161-186 https://doi.org/10.1023/B:GEGE.0000018365.84174.ea
  4. Kevin John Ripley, "The performance of jacked pipes", University of Oxford, 1989
  5. Paul Norris, "The behaviour of jacking concrete pipes during site installation", University of Oxford, 1992