A Study on the Body Welding Operation Scheduling Considering the Assembly Line's Input Sequence in Construction Equipment Manufacturing

건설기계 조립 라인 투입 순서를 고려한 제관 공정 생산 스케줄링에 관한 연구

  • 김기동 (강원대학교 산업공학과) ;
  • 최호식 ((주)인포미아 컨설턴트)
  • Published : 2007.02.28

Abstract

The body of an excavator, one sort of the construction equipment, consists of mainframe part, track frame part, boom part and arm part. The all parts are manufactured in the body welding operation. The scheduling in the body welding operation of a construction equipment manufacturing is to take all the various constraints into consideration. The offset time, due date, daily capacity of operations, daily jig's capacity, precedence relation, outsourcing, alternative resource and all of the shop floor environment should be considered. An APS(Advanced Planning & Scheduling) system is a proper and efficient system in such circumstance. In this paper, we present an APS system, the optimal scheduling system for the construction equipment manufacturing specifically for the body welding operation, using ILOG Solver/Scheduler. ILOG Solver/Scheduler is a general purposed commercial software which supports to find a feasible or optimal solution using object oriented technique and constraints satisfaction programming, given constraints and objectives.

Keywords