Abstract
In order to assess the on-site applicability of 3D absolute displacement monitoring of tunnel using digital photogrammetry, the displacement of the optical target placed at the measurement section was investigated, as planned in the OO tunnel construction site. The targets on 3 measurement lines only were considered for each point of measurement for the reconstruction of 3D cubic model for the digital vision monitoring. For each 3D model, 3 or more images have to be obtained at each point. On the last 2 measurement lines, 6 targets (crown, left and right walls) were continuously overlapped to construct 3D models so that 6 or more apices can be shared by 2 3D models. In order to compare the measurement methods of 3D absolute displacements in tunnel excavation, i. e, total station and digital image measurement, both the digital image measurement and optical measurement were conducted for 10 times in the same work section. The time and measurement results of both methods were compared.
디지털 영상을 통한 터널 내공의 3차원 절대변위 계측의 현장 적용성 검토를 위해 OO터널 현장에 계획된 내공변위 계측단면 상에 위치한 광파 타겟의 변위를 측정하고자 하였다. 디지털 영상 계측을 위한 3차원 입체모델 생성을 위해 측정위치마다 3개의 측선까지의 타겟만 고려하였다. 하나의 입체모델의 생성을 위해서 각 위치에서 3장 이상의 디지털 영상을 획득하여 입체모델을 구성하였으며, 마지막 2개 측선에서의 6개 타겟(천단, 좌우 측벽)을 계속 중첩시켜가며 다음 입체 모델을 구성하여 6개 이상의 정합점이 두 입체모델에서 공유될 수 있도록 하였다. 광파 계측과 디지털 영상계측을 통한 터널 시공 중 암반의 3차원 절대변위 계측 방법을 비교하기 위해 10회에 걸쳐 디지털 영상 계측과 광파 계측을 동일한 구간에 동시에 적용하였다. 각 방법을 사용한 계측에 소요되는 시간과 계측결과를 비교하였다.