Abstract
The duration of highrise building projects is more shorter than its increasing of the numbers of floors. The project is liable to overrun of the time in which the project must be complete. AS highrise buildings are increased, time management has been reorganized as critical success factor. To improve time management, time management softwares are introduced and the software's education is made lively in construction company. However a large amount of time management works still have been based on not the software but scheduler's experience. We often can find the time overrun risk of highrise building because of the shortage of scheduler's experience. To diminish the mistake of the scheduler who does not have much experience, we suggested HRB Expert which uses expert's knowledge to make the time plan of highrise building. We made an example of knowledge acquiring and knowledge usage which cased on reinforced concrete work of highrise building by literature review and interview with scheduling expert. The precision of time plan will be enhanced and time overrun will be prevented on condition that HRB Expert is constructed and used
초고층 건축물은 층수의 증가에 비해서 공기의 증가가 작기 때문에 공기초과가 발생하기 쉽다. 최근 초고층 프로젝트의 증가에 따라 공정계획의 중요성이 증대되고 있으며 공정관리를 개선하기 위해서 공정계획 소프트웨어의 도입과 교육이 활발히 이루어지고 있다. 하지만 공정계획의 많은 부분은 아직도 계획자의 경험에 크게 의존하고 있다. 따라서 새로운 자재, 장비 및 공법이 도입되는 초고층 프로젝트는 공정 계획자의 경험이 부족할 경우, 경험 미숙으로 인한 공기초과가 발생하기 쉽다. 공정 계획자의 경험 미숙으로 인한 공정계획의 편차를 줄이기 위한 방안으로 본 연구에서는 전문가의 경험적 지식을 초고층 공정계획 작성에 활용하는 방안을 제안하였다. 사례연구에서는 초고층 골조공종을 대상으로 하여 본 연구에서 제안한 초고층 공정계획 지원시스템의 지식획득과 지식활용방안을 고찰하였다. 본 연구에서 제안한 지식획득과 지식활용을 토대로 초고층 공정계획 지원시스템을 구축하여 활용한다면 초고층 공정계획의 정확성을 높일 수 있으며 공기초과를 예방할 수 있을 것이다.