Abstract
It is true that SOC facilities, such as dams, need long life cycles since more time has to be invested for the phases of planning, examination, feasibility study, design, contract, construction, and maintenance. This longer life cycle is easily exposed to the risk. And thus, brings additional cost by the delayed project, convenient loss according to the additional run of use, and benefit lose of not to using the facilities. So, the purpose of this study is to try to find a solution to reduce these time consuming problems which could diminish the whole national competition. Hence, this study is to show efficient, systematical project performance and network model by using reciprocal analyses between the construction period and cost based on economical analysis of each phase of life cycles. In addition, on the basis of these outputs, the Fast Track Method is suggested as an alternative solution as a new Approach in Life Cycle's Analysis.
이 연구의 목적은 사회간접자본의 대표적인 시설인 댐과 같이 기획, 조사, 타당성분석 단계에서부터 설계, 계약, 시공 및 유지관리단계까지 건설 생애주기가 긴 경우 Risk에 노출되는 시간 또한 길어져 건설기간 지연에 따른 비용증가는 물론 적기 미 준공시의 증액비용과 이용연기에 따른 편익손실로 국가 전체의 경쟁력을 저하시킴으로 이들 문제점을 감소시키는 방법을 모색하는 것이다. 이에 본 연구에서는 생애주기 각 단계별로 경제성분석을 통한 공기와 비용을 연계 분석하여 효율적이고 체계적인 사업수행단계 및 건설공정 Network모델을 도출하고 이 성과를 토대로 생애주기분석에 있어 Fast Track기법을 적용하는 하나의 새로운 방안으로 제안하고자 한다.