A Study on the Improvement of Construction Progress Management for EVMS

공정-원가 통합관리를 위한 진도관리 개선 방안

  • Published : 2002.08.01

Abstract

The Ministry of Construction-Transportation released a plan about EVMS in 1993 in order to prepare measures for an efficient public construction project, and prepared an enforcement proposal concretely in June for 2000 years, and have enforce a public project by an example with a target. Therefore, accurate analysis and evaluation about field progress are required for efficient management of a building construction, and must be established building construction management system for fast action about a problem However, unified management cannot be consisting because a work progress system is different from details estimate system within a country. and There is not still a definite standard in progress measurement for an application of EVMS. A purpose of this study is to present an improvement about a problem of progress measurement for an application of EVMS. The contents of a study, inquired into a progress measurement method and a standard to use in the field of a public construction and private construction and Checks a problem and presented an improvement item necessary for and is as follows. $\circled1$ must establishes a control account and progress measurement standard. $\circled2$ must manage progress in a activity viewpoint. $\circled3$ must use an accurate CPM process management technique.

Keywords

References

  1. 박홍태, "건설공정 관리학 -이론과 실제-", 기문당, 2000.
  2. 이복남, "건설공사 진도 및 기성고 산정 방법 개선", 건설산업연구원, 1997
  3. 이유섭, "공정.공사비 통합관리(EVM)을 통한 건설사업 관리 선진화 방향", 한국건설기술연구발표회 제12회.
  4. LG건설(주), "공사계획과 관리기법", 1994
  5. 정영수.이영환, "EVMS 개념의 이해와 활용방안", 건설산업연구원, 1999
  6. 한국전력공사, "진도율관리", 울진원자력 3 ,4호기 공정관리 절차서
  7. 한양대학교 건설사업연구실, "EVMS기초모델연구보고서", 2000.
  8. DAU, "Basics of Earned Value Management"
  9. LA CMTA, "Earned Value Clear and Simple" , 1999
  10. Quentin W. Fleming, "Earned Value Project Management" , 1996