Abstract
This study is to understand the effect of the vibration and the stress changes due to the excavation of 2 arch parts of a tunnel, which is a Gyungbu Express Railway tunnel, on the tunnel itself and adjacent slopes in advance, and to analyze the stability. For the estimation of ground conditions, borehole tests, borehole camera logging and seismic logging were performed. Ground properties at a specific location were determined as input constants by performing 2 dimensional analyses with possible ranges of uncertain ground properties. Static and pseudo-static (due to blasting vibration) factors of safety were calculated. The behavior of the tunnel and its vicinity due to the tunnel excavation were predicted by 3 dimensional analyses. It was also tested whether the support system was proper.
본 연구는 한 경부 고속철도 터널의 NATM 굴착에 의한 2 arch 확공 굴착 시 발생되는 진동 및 응력의 변화가 터널 및 인근 사면에 미치는 영향을 사전에 파악하여 안정성을 검토하는 데에 그 목적이 있다. 지반물성치를 산정하기 위해 시추공 조사, TV검층 및 속도검층을 실시하였다. 2차원 해석을 통해 불확실한 지반의 물성을 변수로 간주하고 가능한 범위 내에서 해석을 수행함으로서 특정한 지반 물성이 입력 정수로서 결정되었다. 정적 및 발파 진동에 의한 준-정적(pseudo-static)안전율을 계산하였으며, 3차원 해석을 통해 터널굴착으로 인한 터널 및 터널 주변의 거동과 터널 지보재의 적정성 여부를 조사하였다.