Case Studies on Applications of Convergence Measurement Systems at the Stages of Tunnel Construction and Maintenance
터널 시공 및 유지관리 단계 내공변위 계측시스템 적용사례 연구
- Published : 2000.12.27
Abstract
Three-dimensional total station system which integrated the instrument with Target Pin and TEMS 3D software developed by SKEC R&D center was applied to a tunnel excavation for monitoring of convergence and crown settlement. The efficiency of the system was proved as the result in the aspects of exact monitoring and prediction of rock conditions ahead of the face. To monitor the behavior of tunnel lining at the maintenance stage, DOCS system was applied to the subway tunnel section. Such many effects as the vibration of sensors, verification of the system efficiency, the effect of test trains operation, the variation of temperature and the effect of high voltage was checked. Thus the management scheme for tunnel maintenance was laid out as a proposal.
3차원 광파기 계측장비와 당사에서 개발한 핵심부품인 Target Pin 및 자료처리 분석프로그램 TEMS3D을 통합한 3차원 광파기 계측시스템을 구축하여 터널의 시공중 내공변위 및 천단침하를 계측하였다. 적용결과 천단침하 계측 및 전방지반 예측 측면에서 시스템의 효용성을 검증하였다. 터널의 유지관리 단계의 내공변위 계측을 위해 DOCS시스템을 지하철 단면에 적용하여 계측치의 진동, 시스템의 검증, 열차 운행, 터널내 온도변화 및 고전압에 의한 영향을 검토하여 향후 유지관리 방안을 제시하였다.
Keywords