Abstract
Because of the Keumkangsan-Dam and the Peace-Dam constructed in recent years, it is expected that the peak flood discharge and the peak flood stage at the Hwachun-Dam site have been changed. In this study, two methods were used to simulate and compare the effects of the upstream dam construction on the change of the discharge and the stage. One is the storage function method widely used for the hydrological routing in this country. The other is the DWOPER (Dynamic Wave Operational Model) package developed by the U.S. NWS for the hydraulic routing. Flood routing simulations have been performed on four different scenarios:1) Before the construction of the Keumkangsan-Dam and the peace-Dam, 2) The exclusion of the Keumkangsan-Dam watershed (before the construction of the Peace-Dam), 3) The exclusion of the Keumkangsan-Dam watershed (after the construction of the Peace-Dam), 4) The exclusion of the Peace-Dam watershed. The results of the four test cases from the two methods show that the peak flood discharge and the peak flood stage at the Hwachun-Dam site are reduced due to the construction of the Peace-Dam. From these findings, it is suggested that the operational criteria for the optimal dam-operation of the hwachun-Dam need to be modified.
화천댐 상류에는 최근 금강산댐과 평화댐이 건설되었으며 이로인해 홍수유출 및 수위에 큰 변화를 보여왔다. 본 연구에서는 가용한 유역 자료를 사용하여 상류조건의 변화에 따른 화천댐으로의 유입량 및 수위 변화를 모의하였다. 모의를 위해서는 수문학적 추적 방법중 저류함수법과 수리학적 홍수 추적 방법중 미국 NWS의 DWOPER(Dynamic Wave Operational Model)Package를 사용하였다. 홍수 추적은 1) 금강산댐과 평화댐 건설전, 2) 금강산댐 유역제외(평화댐 건설전), 3) 금강산댐 유역제외(평화댐 건설후), 4) 평화댐의 수문폐쇄시등의 4가지 경우에 대하여 모의하였다. 그 결과 상류댐의 건설로 인해 화천댐 유역의 유입량과 수위가 감소되는 것으로 나타났다. 이같은 결과는 화천댐의 최적운영을 위하여 새로운 댐 조작기준의 설정이 필요함을 의미한다고 사료된다.