A Study on an application of PERT/CPM for process Management

공정관리를 위한 PERT/CPM 활용에 관한 연구

  • Published : 1983.12.01

Abstract

In this paper, I have approached the problem of scheduling that can be reasonably cost down and duration down in the tenement house by using PERT/CPM technics. The tenement house of 'M' construction company consistute 78 element workings in total. I made out the net-work scheduling through 78 element workings, after calculating by computer, G-COS 101, I reduced the duration and cost by MCX, and then enforced from the least cost slope to six times. Resulty, I attained PERT/CPM scheduling for construction scheduling ; a) Make Possible the effectiveness budgeting control b) How the scientific materials c) Make possible the reasonably decision making d) Strengthen the material control by relevance of element workings e) Make possible the duration down through the least cost.