Enhancing Program Risk Management: A Social Network Approach

  • Wenxin SHEN (Department of Construction Management, School of Economic and Management, Beijing Jiaotong University) ;
  • Xiaofan ZHAI (Department of Logistics Management, School of Economic and Management, Beijing Jiaotong University) ;
  • Jingjie XIONG (Department of Construction Management, School of Economic and Management, Beijing Jiaotong University)
  • Published : 2024.07.29

Abstract

Program management presents unique challenges due to the complexity of interrelated projects and increased stakeholder engagement. While existing literature mainly focuses on project-level risk management, inter-project risks remain underexplored. This research addresses this gap by proposing a program risk analysis method that integrates project interdependence and stakeholder engagement. Leveraging social network analysis, the model enhances program risk management efficiency by identifying four types of inter-project risks and suggesting tailored response strategies. Through a case study of the Expo 2020 construction program, the effectiveness of the framework is demonstrated. This study enriches program and risk management literature, deepening our understanding of enhanced risk management in multi-project contexts.

Keywords

Acknowledgement

The support of National Natural Science Foundation of China (Grant Nos. 72201027) is gratefully acknowledged.

References

  1. A. Davies, I. Mackenzie, Project complexity and systems integration: Constructing the London 2012 Olympics and Paralympics Games, Int. J. Proj. Manag. 32 (2014) 773-790.
  2. W. Shen, W. Ying, Large-scale construction programme resilience against creeping disruptions: Towards inter-project coordination, Int. J. Proj. Manag. 40 (2022) 671-684. https://doi.org/10.1016/j.ijproman.2022.06.004.
  3. L. Luo, G. Qiping Shen, G. Xu, Y. Liu, Y. Wang, Stakeholder-Associated Supply Chain Risks and Their Interactions in a Prefabricated Building Project in Hong Kong, J. Manag. Eng. 35 (2019) 1-14. https://doi.org/10.1061/(asce)me.1943-5479.0000675.
  4. N. Xia, R. Zhong, C. Wu, X. Wang, S. Wang, Assessment of Stakeholder-Related Risks in Construction Projects: Integrated Analyses of Risk Attributes and Stakeholder Influences, J. Constr. Eng. Manag. 143 (2017) 1-11. https://doi.org/10.1061/(asce)co.1943-7862.0001322.
  5. H. Zhou, S. Tang, W. Huang, X. Zhao, Generating risk response measures for subway construction by fusion of knowledge and deep learning, Autom. Constr. 152 (2023) 104951. https://doi.org/10.1016/j.autcon.2023.104951.
  6. S. Moon, S. Chi, S.B. Im, Automated detection of contractual risk clauses from construction specifications using bidirectional encoder representations from transformers (BERT), Autom. Constr. 142 (2022) 104465. https://doi.org/10.1016/j.autcon.2022.104465.
  7. R.J. Yang, P.X.W. Zou, Stakeholder-associated risks and their interactions in complex green building projects: A social network model, Build. Environ. 73 (2014) 208-222. https://doi.org/10.1016/j.buildenv.2013.12.014.
  8. A.E. Yildiz, I. Dikmen, M.T. Birgonul, K. Ercoskun, S. Alten, A knowledge-based risk mapping tool for cost estimation of international construction projects, Autom. Constr. 43 (2014) 144-155. https://doi.org/10.1016/j.autcon.2014.03.010.
  9. S.P. Borgatti, M.G. Everett, Network analysis of 2-mode data, Soc. Networks 19 (1997) 243-269. https://doi.org/10.1016/S0378-8733(96)00301-2.
  10. X. Wang, N. Xia, Z. Zhang, C. Wu, B. Liu, Human Safety Risks and Their Interactions in China's Subways: Stakeholder Perspectives, J. Manag. Eng. 33 (2017) 1-15. https://doi.org/10.1061/(asce)me.1943-5479.0000544.
  11. T. Yu, G.Q. Shen, Q. Shi, X. Lai, C.Z. Li, K. Xu, Managing social risks at the housing demolition stage of urban redevelopment projects: A stakeholder-oriented study using social network analysis, Int. J. Proj. Manag. 35 (2017) 925-941. https://doi.org/10.1016/j.ijproman.2017.04.004.
  12. F.D. Patterson, K. Neailey, A risk register database system to aid the management of project risk, Int. J. Proj. Manag. 20 (2002) 365-374. https://doi.org/10.1016/S0263-7863(01)00040-0.
  13. L.C. Freeman, Centrality in Social Networks Conceptual Clarification, Soc. Networks 1 (1979) 215-239. https://doi.org/10.1016/0378-8733(78)90021-7.
  14. W. Shen, J. Xue, Managing project-to-project interfaces for large-scale programmes: A network study in world expo 2020, Int. J. Proj. Manag. 41 (2023) 102438. https://doi.org/10.1016/j.ijproman.2023.102438.