A STUDY ON SPACE ZONING BY COMPUTING IDLE-TIMES IN CONSTRUCTION PROCESSES

  • Sang-Min Park (School of Architecture and Civil Engineering, Kyungpook National University) ;
  • Won-Suk Jang (Department of Civil Engineering, Yeungnam University) ;
  • Dong-Eun Lee (School of Architecture and Civil Engineering, Kyungpook National University)
  • Published : 2013.01.09

Abstract

An inappropriate space zoning plan causes the unnecessary transportation of construction material and equipment among work areas and increases the disorder of work space. Space zoning is an essential operation management technique which contributes to reduce the process and/or operation idle-time. This paper introduces a method that computes the idle-times between construction operations (or processes) by using Web-CYCLONE. It allows computing with idle-times that affect the construction productivity. Using the idle time between operations and between processes, it computes the optimal number of zones and finds the optimal combination of zones that minimize the idle times. The method contributes to minimize the idle times relative to the operation schedule using complete enumeration. This paper presents the system prototype in detail. A case study is presented to demonstrate the system and verifies the validity of the model. It allows a project manager to establish space zoning plan that effectively segregates a project into optimal number of construction zones and to assign the constrained resources (e.g., laborer, equipment).

Keywords

Acknowledgement

This research was supported by Basic Science Research Program through the National Research Foundation of Korea (NRF) funded by the Ministry of Education, Science and Technology (No. 2012R1A2A2A02003265).