An experimental construction of railway steel plate girder strengthen adding ballast system by transport equipment

선로 이송 가설공법을 적용한 철도판형교 유도상화

  • 민지홍 (한양대학교) ;
  • 서종원 (한양대학교 건설환경공학과) ;
  • 장형식 (한국철도시설공단 시설운영본부 시설관리처 시설계획팀) ;
  • 박준원 (한국철도시설공단 영남지역본부 건설처 공사팀)
  • Published : 2011.05.26

Abstract

It has been applied using cranes or insertion methods to install heavy structures to strengthen existing railway bridges. These methods are uneconomical because of two reasons. The first one is it is required to construct approach roads for heavy equipment and/or working yard. The second one is the electric lines shall be cutoff during construction. Both require additional construction cost and duration. In this study, new transport equipment was developed which can be applied to heavy structures up to 100 ton. Using this method, the heavy structure can be loaded into the new transport equipment at working yard and transported to the working site. This method can be applied, but not limited to railway bridge or roadbed rehabilitation. It was found that the precious construction can be achieved to install heavy structure using this method. The experimental construction to make non-ballast girder bridge composite with new pc deck slab using this method was carried out for Jewon bridge. The example bridge is in extreme condition because it locates above national road #38 within extreme transition curve and has 10 ‰ slope and skew. The experimental construction results were satisfactory both for safety and construction precision.

Keywords