TACT Modification Methods for Responding to Delay in Winter Season

동절기 공정지연 대응을 위한 TACT 공정 조정방안

  • 김대규 (서울시립대학교 건축학부 건축공학전공) ;
  • 정용준 (서울시립대학교 건축학부 건축공학전공) ;
  • 이준호 (서울시립대학교 건축학부 건축공학전공) ;
  • 문현석 (서울시립대학교 건축학부) ;
  • 구교진 (서울시립대학교 건축학부) ;
  • 현창택 (서울시립대학교 건축학부)
  • Published : 2011.11.18

Abstract

Construction projects are being more complicated in proportion to the economic development. Process management is a critical issue in the construction that decides success of a project. Especially, a TACT method which divides and manages resources to repeat each activity is more important. Although becoming an issue dealing with the delay at winter season, it is not property developed. This paper suggests 'activity priority method' and 'TACT unit method' through case study. We validate necessity and efficiency of the TACT method through simulations and a survey. We expect cost reduction by decreasing unnecessary spending.