Database Program for Managing Management Resources: General Contractor's Perspectives

  • Yong-Woo Kim (College of Built Environments, University of Washington) ;
  • Sungwon Shin (Project Innovation Team, GS Engineering and Construction)
  • Published : 2009.05.27

Abstract

General contractors' overhead costs are increasing relative to direct costs. However, it is difficult to apply the traditional activity-based costing directly to the construction site overhead costing because the resource consumption rate per each activity is varied depending on the attributes of activities. The research develops a methodology of hybrid cost allocation system when resources are assigned to cost objects unlike the traditional activity-based costing. The study also develops a database program and demonstrates how it can be applied to the construction projects using a case study.