The Study on Countermeasures of Electromagnetic Force by Three Phase Short-Circuit Test of Cable

케이블 삼상단락 실증시험을 통한 전자력 대책방안 검토

  • Published : 2009.07.14

Abstract

Even though underground transmission cable is an essential transmission method to supply stable power for downtown and population center, interaction of electromagnetic force from fault current is very large comparing to overhead transmission line due to restricted installation space such as tunnel, etc. and close consideration is required for it. This paper presents countermeasures to reduce and release the effect of electromagnetic force with rope binding and installation of spacer and describes its efficacy through three phase short-circuit test, which will be utilized as basic materials for improvement and development of cleat, hanger, etc. to reduce and release effect of electromagnetic force in the future.

Keywords