ANALYSIS AND IMPROVEMENT OF FINISHING WORK PROCESS FOR COST MANAGEMENT (FOCUSED ON INDOOR FINISHING WORK OF APARTMENT)

  • Hoon-Ku Lee (Dept. of Sustainable Architectural Engineering, Hanyang Univ.) ;
  • Yoon-sun Lee (Sustainable Architecture Professional Education Center, Hanyang Univ.) ;
  • Ja-Young Yoon (Dept. of Sustainable Architectural Engineering, Hanyang Univ.) ;
  • Jae-Jun Kim (Dept. of Sustainable Architectural Engineering, Hanyang Univ.)
  • 발행 : 2007.03.01

초록

Apartment housing in the Korean domestic construction industry has had various and high-quality finishing work since the enforcement of price deregulation in 1998. Before the enforcement of price deregulation, feasibility studies of housing projects have not had particular difficulties as uniform description of finishing work items were reflected and finishing work cost also was equalized. However, the recent distinction of finishing work based on the same floor plan brings about project cost variation, along with many effects on construction management due to project cost increment. Accordingly, this paper suggests the improved plan of cost management to control the feasibility study result consistently during the life cycle of a project through an analysis based on cost management phase due to cost blackout, appearing at the commencement of a project, cost gradation caused by high-quality finishing work item, and cost reduction due to the degradation of finishing work after analysis of current apartment construction process focused on finishing work using the IDEF process analysis technique.

키워드

과제정보

This work was supported by the SRC/ERC program of MOST/KOSEF (R11-2005-056-03001)