The Application of TMP Method on Suk-San Highway Bridge
석산육교 공동충전을 위한 가소상 모르타르 충진(TMP)공법 적용
- Published : 2006.05.11
Abstract
Suk-San highway bridge, located on a soft ground environment, had been examined the current condition of settlement estimation throughout G.P.R(Ground Penetrating Radar), general observation and visual observation(video camera & scope). According to the above observations, the ground of this area has sunk about thirty centimeters since 1996. Also, currently, Suk-San highway bridge has been disjoining the gap between the structure and ground. Therefore, it is necessary to fill it up the gap. The purpose of this paper is to report the effects of Sunk-San highway bridge was observed by G.P.R. & general observation etc. and to present the results of repair of Suk-San highway bridge filling the gap up.