한국콘크리트학회:학술대회논문집 (Proceedings of the Korea Concrete Institute Conference)
- 한국콘크리트학회 2006년도 춘계학술발표회 논문집(I)
- /
- Pages.626-629
- /
- 2006
석산육교 공동충전을 위한 가소상 모르타르 충진(TMP)공법 적용
The Application of TMP Method on Suk-San Highway Bridge
- 발행 : 2006.05.11
초록
Suk-San highway bridge, located on a soft ground environment, had been examined the current condition of settlement estimation throughout G.P.R(Ground Penetrating Radar), general observation and visual observation(video camera & scope). According to the above observations, the ground of this area has sunk about thirty centimeters since 1996. Also, currently, Suk-San highway bridge has been disjoining the gap between the structure and ground. Therefore, it is necessary to fill it up the gap. The purpose of this paper is to report the effects of Sunk-San highway bridge was observed by G.P.R. & general observation etc. and to present the results of repair of Suk-San highway bridge filling the gap up.
키워드