Effect analysis of distributed jointing method on underground Transmission Cables

지중송전케이블의 분산식 접속법에 따른 영향 분석

  • Published : 2002.11.15

Abstract

The distributed jointing method is used in the underground tunnel due to narrow space of jointing. This method causes non-uniform length between cable joints. It has an effect on the sheath circulating current and the induced voltage. Furthermore the distributed jointing method may cause transient overvoltage resulting from lightning in underground cable which is connected with overhead line. The author diversely studied the sheath circulating current and induced voltage on underground cable depending on the distributed jointing length under the normal and the transient circumstances. The various simulation results really improve the cable system utility.