Assessment of Three-Phase Actuated Signal Operation at Diamond Interchanges

다이아몬드 인터체인지의 3 현시 신호운영 평가

  • Published : 2002.02.01

Abstract

The performance of two single-barrier three-phase actuated control systems at diamond interchanges was evaluated for various traffic conditions. To emulate the actuated signal control, hardware-in-the-loop system combined with CORSIM simulation program was used. Two performance measures, average delay and total stops, were used for the evaluation process. Results showed that the two three-phase systems gave similar performance in terms of average delay, but not stops. The delay performance of each phasing system was generally dependent on the traffic pattern and ramp spacing. The total stops decreased as the spacing increased, and it was the most sensitive variable that can differentiate between the two three-phase systems. It was also shown that the hardware-in-the-loop control could provide a good method to overcome the limitations of current simulation technology.

Keywords