공기지연에 따른 클레임 대응방안에 관한 연구 - 지체상금을 중심으로 -
A Study on a System of Resolving Claim according to the Delay of Construction Projects - Focus on Liquidated Damages -
초록
The delay of the completion of the construction project occurs frequently because the origin schedule is affected by numerous factors that contribute to the overall delay in completing the project. But in our country. the dealing with a claim is not sufficient yet by reasons of fairl relation between owner and constructor, cognitive shortage in claim, and such. especially they have make a wrong application of baseless the rule. In this study. we make a rational model ; that includes calculating of dispute costs, and suggest the solution and the prevention for claim by considerating the law followed liquidated damages.