A Study on the Estimation Standard of Optimal Construction Duration for Reinforced Concrete Apartment House

철근콘크리트조 공동주택 적정공기 산정기준에 관한 연구

  • Published : 2001.11.01

Abstract

At the beginning of construction, the estimation for the construction duration is very important to effectively control and use labors, builder's equipment, permanent and temporary materials, supplies and utilities, and money. In spite of the importance of the estimation for the construction duration, there is no estimation standard of optimal construction duration in korea. The purpose of this study is to suggest the estimation standard of optimal construction duration that is reasonable and systematical through developing the method for estimating, the construction duration. it is expected to be helpful for estimating, planning and scheduling. The analysis is executed the existing estimation standards and consulting the results of the interviews with the on-site engineers and the concrete compressive stress tests.

프로젝트 초기단계에 공기산정이 적절히 이루어져야만 프로젝트 진행과정에서 인력, 자재, 장비 등을 효율적으로 이용할 수 있으며 자금을 적절하게 배분할 수 있다. 그러나 아직 국내에서는 기준으로 삼을 만한 공기산정 기준이 없는 실정이다. 본 연구에서는 현재의 불명확한 공기산정방식을 개선함으로써 프로젝트 초기단계에서 적정공기를 예측하고 타당한 공정계획을 수립할 수 있도록 합리적이고 체계적인 공기 산정기준을 제시하고자 한다. 이를 위하여 본 연구에서는 기존 산정기준의 비교 분석을 통하여 개선방향을 도출하고, 현장기술자들과의 면담조사, 현장실험, 기존 연구자료 등을 활용하여 적정공기 산정기준을 제시하였다.

Keywords