A study activating devices in scheduling management for analyzing progress payment in Korea

기성지급방식 비교분석을 통한 국내 공정관리 활성화 방안에 관한 연구 -경부고속철도 공사와 대만 고속철도공사 비교 중심으로-

  • 이태식 (한양대학교 토목환경시스템공학과) ;
  • 김영현 (한양대학교 토목환경시스템공학과 대학) ;
  • 정현진 (한양대학교 토목환경시스템공학과 대학) ;
  • 김영환 (삼성물산 건설부) ;
  • 김대영 (삼성물산 건설부) ;
  • 윤철수 (현대건설주식회) ;
  • 노시현 (현대건설주식회사)
  • Published : 2001.05.01

Abstract

Most payments in domestic construction are issued in lumpsum unit price contracts according to the completed construction rate. This method generates problems in losing time and increased costs for the owner and contactor. In overseas projects, payments are issued in accordance to completed milestones. The milestones themselves base on the original schedule and allow effective schedule management on the tasks. In domestic construction, however, introduction of milestone payments requires enhanced management capability of owners and contractors. Hence, this study investigating how to activate schedule management devices to analyze progress payments in domestic construction.