Restarting Trains Under Moving Block Signaling - An Expert System Approach

  • K, K.-Wong (The Hong Kong Ploytechnic Univ.) ;
  • Akio, Katuki (Kyushu Univ.)
  • 발행 : 2001.10.01

초록

A high peak power demand at substations will result under Moving Block Signalling (MBS) when a dense queue of trains begins to start from a complete stop at the same time in an electrified railway system. This may cause the power supply interruption and in turn affect the train service substantially. In a recent study, measures of Starting Time Delay (STD) and Acceleration Rate Limit (ARL) are the possible approaches to reduce the peak power demand on the supply system under MBS. Nevertheless, there is no well-defined relationship between the two measures and peak power demand reduction (PDR). In order to attain a lower peak demand at substations on different traffic conditions and system requirements, an expert system is one of the possible approaches to procure the appropriate use of peak demand reduction measures ...

키워드