All equipment generally has a specified design service life. As an equipment nears the end of its design service life, replacement must be considered. In some cases, it is possible and more economical to continue the usage of the existing equipment for a longer period. So, replacement should be carefully decided considering the feasibility and economic benefits of the existing equipments' life extension. In this paper, assessment procedure for deciding between life extension and replacement of the electronic control system is presented with an application example. In particular estimation of the electronic control system's remaining life is focused on.