석탄화력 발전소의 LOAD RUN BACK에 관한 연구

A Study on the Load Run Back Control of a Coal Fired Power Plant.

  • 발행 : 1989.07.21

초록

This work describes the imortance of the load run back control of a thermal power plant which has a serious effect on a power system, and shows the load run back tests results which was carried out at BORONG Thermal Power Plant, finally suggests what control circuits should be modified in the plant control system in order to prevent plant trip in case of auxiliary machine failure.